On October 17, Hebei Development and Reform Commission issued a notice on matters related to the price bidding of new energy mechanism in 2025-2026, and decided to carry out the price bidding of incremental new energy project mechanism in 2025-2026.
Among them, the scale of electricity. The total power generation scale of Hebei Southern Power Grid is 29.087 billion kWh (calculated by the whole year, the same below), of which wind power is 24.583 billion kWh and photovoltaic power is 4.504 billion kWh; The total scale of power generation mechanism in North Hebei Power Grid is 35.787 billion kWh, of which wind power is 21.935 billion kWh and photovoltaic power is 13.852 billion kWh.
Declaration of adequacy ratio. The lower limit of the adequacy rate of wind power and photovoltaic bidding declaration is 125%. The upper limit of the proportion of electricity declaration for a single project mechanism is 80%. The upper and lower limits of wind power and photovoltaic bidding
in Hebei Southern Power Grid are 0.2-0.3644 yuan per kilowatt hour; The upper and lower limits of wind power and photovoltaic bidding in North Hebei Power Grid are 0.2-0.372 yuan per kilowatt hour. The implementation period of wind power and photovoltaic power is 10 years and 12 years respectively. The benchmark price of coal-fired power generation in
Hebei Southern Power Grid is 0.3644 yuan/kWh, and that in Hebei Northern Power Grid is 0.372 yuan/kWh.