Go straight to Central Asia! China Nengjian 300 MW Photovoltaic Power Plant EPC General Contracting Procurement Project Released!

2025-06-24 18:59:53

On June 23, China Nengjian Electronic Procurement Platform issued a pre-qualification announcement for EPC general contracting of photovoltaic power plants for Navoi Integrated Energy Project in Uzbekistan.

On June 23, China Nengjian Electronic Procurement Platform issued a pre-qualification announcement for EPC general contracting of photovoltaic power plants for Navoi Integrated Energy Project in Uzbekistan.

The announcement shows that the Navoi Integrated Energy Project is located about 56 km north of Navoi City, Navoi State. A new 300 MW AC PV power station is planned to be built. One 150MW/300MWh

The scope of this tender is a new 300 MWac photovoltaic power station (including 220kV booster station) and EIF facilities. The AC side capacity of the photovoltaic power station is 300MWac . The installed capacity on the DC side is about 363.

The project adopts 620 Wp monocrystalline double-sided modules , flat single-axis tracking brackets and string inverters. The project will be tendered for

about 0.EIF facilities, as shown in the following figure:

PV power station is scheduled to be completed on July 30, 2026." The EIF facility is scheduled to complete the commissioning and operation of the EIF facility before July 30, 2026 and pass the government acceptance.

In addition, 220kV switchyard of EIF main substation, Necessary supporting facilities and "π" connecting lines shall meet the requirements of Navoi PV Power Station and Navoi that this tender requires the respondent to have undertaken at least one 300MWac photovoltaic power station (including 220kV booster station) EPC project performance or at least one 220kV and EPC project performance of Shanghai power transmission and transformation line.

At the same time, the respondent shall be able to accept the payment mode of the contract price of the project:

onshore contract (including EIF facilities) : 10% of the advance payment, 3% of the quality guarantee deposit, and the remaining contract payment shall be paid after the commercial operation of the project (COD) (the specific scheme shall be subject to the contract).

Offshore contract : 10% of the advance payment and 3% of the quality guarantee deposit for PV modules , brackets and module cleaning robots. The remaining contract amount shall be paid before the delivery of each batch; 5% of the advance payment for PV inverter and 3% of the quality guarantee deposit shall be paid before the delivery of each batch; The advance payment for other equipment shall be 10% , the quality guarantee deposit shall be 3%, and the remaining contract payment shall be paid after the commercial operation of the project (the specific scheme shall be subject to the contract). The specific requirements for the qualification of the

respondent are shown in the following figure:

not exceed 2 .". For the joint venture of the same discipline, its qualification level shall be determined according to the unit with lower qualification level; for the joint venture of multiple disciplines, its qualification shall be determined according to the division of labor agreed in the joint venture agreement.

Submission deadline/bid opening time: 11:00, July 21, 2025 (subject to the actual release time of the procurement platform)

In recent years, China Nengjian has been looking overseas, focusing on Central Asia and other markets along the Belt and Road, and vigorously expanding new energy markets such as photovoltaic and wind power. During the second summit between China and the five Central Asian countries held on

June 16-18, Nengjian Haitou, a subsidiary of China Energy Construction Group, successfully signed the power purchase agreement for the 300 MW photovoltaic distribution and storage project in Turkistan, Kazakhstan, the shareholder agreement for the 500 MW wind power distribution and storage project in Karaganda, and the Central Asia ." During the first China-Central Asia Summit in May 2023, Uzbek President Mirziyoyev witnessed the foundation laying ceremony of the 1GW photovoltaic project in Uzbekistan . The total investment of the project is 6.