On October 11, Guizhou Provincial Office of Industry and Information Technology issued the Announcement on the Capacity Transfer Scheme of 2 # New Dry Cement Production Line with Daily Output of 4500 Tons of Clinker of Zunyi Conch Panjiang Cement Co., Ltd. According to the Announcement, the capacity index of Zunyi Conch Panjiang 4500 t/d production line is replaced by two clinker production lines of Yingde Conch in two parts. Zunyi Conch Panjiang 4500t/d clinker production line will be shut down on September 1, 2025 and planned to be dismantled before October 31, 2026. According to
the data, Zunyi Conch Panjiang Cement Co., Ltd. is a wholly-owned subsidiary of Anhui Conch Cement Co., Ltd.