Clinker production line projects that have been completed but not put into production have been "upgraded" to be under construction, and are they unwilling to be included in the list of shutdown?

2024-02-27 14:29:34

Since it has been completed and has not been put into production for a long time, it should be treated as a production line shutdown, but in 2023 it has "risen" to become a project under construction? Is it unwilling to explicitly include it in the list of production lines?

Recently, Gansu Province released a list of the current situation of cement clinker production lines in Gansu Province in 2023. Among them, the 4500t/d cement clinker production line of Gulang Xinmiao Fine Chemical (Group) Co., Ltd. was marked as a project under construction, which was suspended due to the breakdown of the enterprise's capital chain. After consulting the list of the current situation of Gansu cement clinker production line in previous years ,

the author found that the above production line was basically completed and not put into operation in the list of 2022 (last year). The previous two lists have also been basically completed. Since it has been completed and has not been put into production for a long time, it should be treated as a production line shutdown, but in 2023 it has "risen" to become a project under construction? Is it unwilling to explicitly include it in the list of production lines?

In addition, Xiahe Qilianshan Anduo Cement Co., Ltd. has been replaced in the list of cement clinker in 2022 and is to be demolished. Accordingly, by 2023, this production line should be dismantled, or should continue to be dismantled, how can it become a formal "registered permanent residence"?

Linxia Conch Cement Co., Ltd. has announced the cancellation of capacity transfer in the list of cement clinker in 2022 and 2023. The previous year 2022 has cancelled the transfer of production capacity, the second year 2023 should naturally return to the official "account", why can not return, but also continue to cancel it?

According to the Measures for the Implementation of Capacity Replacement in the Cement and Glass Industry, the production capacity of cement clinker and flat glass production lines used for replacement must be compliant and effective, and be included in the list of compliant cement clinker and flat glass production lines in the region announced annually by the provincial industrial and information authorities. Therefore, the production line included in the list must be compliant capacity. Publishing the list of production lines once a year is a serious and rigorous work, and it must be seamless year by year!

All can be viewed after purchase
Correlation

Recently, the overall domestic demand has declined steadily, coupled with the weakening of local cost support, and the price of concrete has been stable and small. From November 14 to November 20, the national concrete price index closed at 112.35 points, down 0.13% annually and 10.08% year-on-year.