Annual output of 3 million tons of cement! Baling Conch Low Carbon Demonstration Plant is expected to be completed and put into operation in March

2024-01-02 09:43:37

It is understood that the Baling Conch Low Carbon Demonstration Plant project started construction in March 2023, with a construction area of nearly 50000 square meters, and three new sets of 4.2 ball mills plus 1.8 roller presses combined with double closed-circuit grinding systems. Construction of 150000 tons of clinker storage, 80000 tons of auxiliary materials storage, cement mill, 100000 tons of cement storage, cement packaging, delivery system and supporting special wharf and production auxiliary facilities. The project is expected to be completed and put into operation in March 2024, with an annual output of 3 million tons of cement, invoice sales of 1 billion yuan and tax revenue of 100 million yuan.

"What specific work has each group accomplished today?" "Refine tomorrow's workload according to the actual situation." "In rainy and snowy weather, please remind workers to pay more attention to construction safety." On the afternoon of December 18, 2023, in the conference room of the project manager department of Baling Conch Low Carbon Demonstration Plant in Yandong Town, Qian Zhulin, deputy director of the raw product department of Jiangsu Baling Conch Cement Co., Ltd., was busy with Jiang Wenjian, project manager of the construction team, reviewing the implementation of the project for one day. According to the weekly construction plan, we should "pass through the hall" one by one, promptly remind the construction safety, pay attention to the construction quality, and ensure the high-quality construction of the project according to the schedule. In

the afternoon, snowflakes were flying around in the howling wind. When the reporter walked into the construction site of the Baling Conch Low Carbon Demonstration Factory project adjacent to Xinyang Port, he saw tower cranes and roaring machines in the factory area, all kinds of building materials were transported accurately with the hoisting equipment, vehicles were traversing, and workers adhered to the front line of the project construction, binding steel bars, cutting steel plates, handling building materials and installing equipment at their respective stations. It is a busy scene of "working hard in the fourth quarter".

It is understood that the Baling Conch Low Carbon Demonstration Plant project started construction in March 2023, with a construction area of nearly 50000 square meters, and three new sets of 4.2 ball mills plus 1.8 roller presses combined with double closed-circuit grinding systems. Construction of 150000 tons of clinker storage, 80000 tons of auxiliary materials storage, cement mill, 100000 tons of cement storage, cement packaging, delivery system and supporting special wharf and production auxiliary facilities. The project is expected to be completed and put into operation in March 2024, with an annual output of 3 million tons of cement, invoice sales of 1 billion yuan and tax revenue of 100 million yuan.

"At present, dormitory buildings, R & D buildings and main projects have been completed and are expected to be completed and put into operation by the end of the year." Jiang Wenjian introduced that at present, 70% of the ceiling keel installation, 70% of the floor tile installation and 60% of the square ground hardening have been completed in the first floor of the R & D building of the project; the transfer station, substation 1 , 2 # wall masonry and secondary structure have been completed; the C35 surface pouring of the F1-F4 section of the surface arc beam has been completed; 70% of 1 # clinker silo grid installation, 90% of 2 # clinker silo grid purlin installation, 70% of 3 # clinker silo steel platform installation and 70% of grid purlin installation are completed.

Quality is no trivial matter, and safety is greater than the sky. The project construction unit has always adhered to the style of "high-quality construction", set up a leading group for project construction, strengthen overall planning and scientific promotion, schedule the project schedule, improve the project quality management system, draw the organizational chart of quality management and occupational health and safety management, all of which are posted on the wall, and set up a pre-shift safety comment desk at the entrance. Strictly implement the "regular meeting system", carry out this week's problem review and next week's plan scheduling, and make every effort to ensure the timely and efficient completion of various construction tasks, so as to ensure the rapid and safe construction of the project.

Strengthening energy conservation and consumption reduction is an important part of promoting the green development of manufacturing industry. "With the goal of" reducing energy consumption and optimizing indicators ", our company will speed up the construction of a new type of scientific and technological chemical plant with" intelligent factory and green industry ", strive to eliminate all the old equipment before, adopt DCS system to control the new production line, save more than 3000 tons of standard coal per year, and accelerate the realization of green development." Talking about the advantages of new projects and new equipment, Qian Zhulin is full of confidence. When

enterprises encounter difficulties, special classes will solve them. In the process of project construction, because many large machines are needed in the early stage of construction, it is easy to cause dust during centralized operation, which may affect the surrounding environment. However, due to the shortage of personnel, the construction team can not solve the dust problem in time in a short time, which affects the progress of the project. After learning about the situation in the first-line service process

, Yandong Town Project Service Team went into the construction site to find out the reasons at the first time, and found that due to the lack of "dust removal vehicle" and "sprinkler" on the construction site, the dust generated by the construction could not be timely "removed with production". Therefore, the special class service personnel invited experts from the district environmental protection department to "consult the pulse" and temporarily borrowed a number of "dust removal vehicles" and "sprinklers" from other project sites, which successfully helped solve this problem and alleviated the "urgent need" of the project construction.

"Since this year, we have continuously strengthened the attitude of" fighting ", the consciousness of" grabbing "and the vigor of" fighting ", set up a special service class for the project of Baling Conch Low Carbon Demonstration Plant at the first time, provided follow-up service throughout the process, assisted the project construction team to complete a series of matters such as formalities, external communication, resource coordination, and so on. Make every effort to provide a good external environment for the smooth construction of the project, and urge the project to be completed as soon as possible and put into full operation to achieve results. Relevant person in charge of Yandong Town said.


All can be viewed after purchase
Correlation