Successful Closure of Rotary Kiln of Chongqing Tongliang Southwest Cement 7300t/d Clinker Project

2024-04-24 09:25:46

The rotary kiln of Chongqing Tongliang Southwest Cement Co., Ltd. with a daily output of 7300 tons of clinker and supporting production line relocation and technical transformation project was successfully closed.

On

20 April, The rotary kiln of Chongqing Tongliang Southwest Cement Co., Ltd. with a daily output of 7300 tons of clinker and supporting production line relocation and technical renovation project, which was constructed by Tianjin Cement Institute, was successfully closed. The size of rotary kiln in the technical transformation project of

Chongqing Tongliang Southwest Cement Co., Ltd. with a daily output of 7300 tons of clinker and supporting production line is φ5.5 × 78 m, and the total weight of cylinder and tire is 695.2 tons.

In order to ensure the safe and smooth completion of the hoisting task of the rotary kiln, the project department has formulated a reasonable construction plan in close connection with the actual situation on site. In the early stage of equipment mobilization, the project team coordinated to overcome the narrow access road and other problems, and used cranes to directly lift the wheel belt, large gear ring and other components from the highway to the front road of the plant. Before the start of the

hoisting operation, the project department organized all the operators involved in the hoisting to carry out safety technical disclosure, and simulated the whole process of hoisting. During the hoisting process, all members of the project team cooperated closely and worked together to achieve the smooth hoisting and closure of the rotary kiln cylinder. The successful hoisting and closure of the

kiln shell is an important node in the whole project, which lays a solid foundation for the realization of the overall goal of the project construction and creates conditions for the smooth progress of the follow-up work. In the future work, the project department will continue to uphold a rigorous working attitude, grasp the progress, ensure quality, promote safety, and make every effort to ensure the smooth realization of the project milestones.