On November 28, the Bureau of Ecology and Environment of the Sinkiang Production and Construction Corps issued three environmental impact assessment documents on the technical renovation project of energy saving and emission reduction for capacity replacement of Yili Qingsong Building Materials Co., Ltd.
The announcement shows that Yili Qingsong Building Materials Co., Ltd. adopts a new dry process cement clinker production process to expand the capacity of existing rotary kilns, eventually forming a production capacity of 3500 tons per day of cement clinker. The project does not increase the labor quota, and the production department adopts the continuous working system of 3 shifts and 2 shifts, with annual operation of 300 days and 7200 hours. The total investment of the
project is 253.27 million yuan, including 38 million yuan for environmental protection, accounting for 15% of the total investment.