On March 22, at the construction site of the first commercial mixing project of Gezhouba Cement Yicheng Green Building Material Industrial Park, the reporter saw that many construction machinery shuttled back and forth, workers put into construction at full capacity, and the construction site was in full swing.
It is understood that the first commercial mixing project of Gezhouba Cement Yicheng Green Building Material Industrial Park is one of the four major projects that Yicheng started in January this year. Since the start of construction, the project construction has run out of "acceleration" with a "struggle" attitude, and is expected to be completed and put into operation in early June.
"There are more than 80 people on site, 5 excavators, 5 cranes and 3 loaders.". Now we are seizing the fine weather and putting in personnel and equipment one after another to catch up with the schedule. Zhang Shuisheng, manager of Gezhouba Lingang Yicheng Building Materials Co., Ltd., said.
Gezhouba Cement Yicheng Green Building Material Industrial Park, with a total investment of 5 billion yuan, includes six sub-projects, namely, machine-made sand and gravel, aggregate production, training and visiting base, distributed photovoltaic, alternative fuel production line, assembly building production line, construction waste disposal project and new environmental protection active calcium production line. The
first phase of the commercial mixing project is the first project of Gezhouba Cement Yicheng Green Building Material Industrial Park, covering 52 mu, with a total investment of about 120 million yuan.
"At present, the main project and ancillary projects have started construction, among which, the mixing building has completed the foundation pouring below positive and negative zero, and the rest of the main project foundation is being excavated synchronously, which is expected to be completed and put into operation in early June." Yu Kangyi, general manager of Gezhouba Lingang Yicheng Building Materials Co., Ltd., said.
With the help of governments at all levels and relevant departments, the project construction has pressed the "acceleration key", and the comprehensive building, central control building and mixing building under construction have taken shape.
It is understood that the first phase of the project will build a green, three-star commercial mixing production line with an annual output of 600,000 cubic meters; the second phase of the project plans to build photovoltaic and energy storage, prefabricated buildings, prefabricated construction and other new building materials, which can provide stable and high-quality building materials for the infrastructure construction of the park and enterprises.
"After the completion of the project, through the integrated sales model, it can promote the development of Gezhouba Cement's main business and aggregate business, achieve annual revenue of more than 100 million yuan, profits and taxes of more than 10 million yuan, and directly and indirectly promote employment of more than 100 people." Yu Kangyi, general manager of Gezhouba Lingang Yicheng Building Materials Co., Ltd., said.