It is understood that a number of recent cement clinker production line construction projects ushered in the latest progress.

Recently, the Department of Ecology and Environment of Hebei Province issued the Announcement on the Acceptance of the 5500t/d New Dry Process Cement Clinker Production Line and the Environmental Protection Demonstration Project of Co-disposal of Solid Waste of Tangxian Jidong Cement Co., Ltd.

Main construction content and scale: Construct a new dry process cement clinker production line with a daily output of 5,500 tons of clinker and a calciner outside the kiln. The kiln tail is equipped with a double-series six-stage low-pressure loss cyclone preheater and a TDF calciner, with an annual output of 1,705,000 tons of cement clinker; It is equipped with a 12MW pure low-temperature waste heat power generation system, a 110KV main substation and supporting production auxiliary facilities, and a production line for the disposal of 800 tons of general solid waste (including domestic garbage and other combustibles) per day. The annual disposal capacity of general solid waste is 240,000 tons; the construction waste crushing system and stacking shed with a daily disposal capacity of 200 tons are constructed, and the annual disposal capacity of construction waste is 60,000 tons. Total investment of the

project: 1,826.55 million yuan, including 650 million yuan of project capital, which accounts for 35.59% of the total investment of the project.

It is understood that a number of cement clinker production line construction projects have recently ushered in the latest progress, specifically:

Fenyi Conch 4500 t/d clinker production line is stepping up construction

. According to yuan Jian, deputy director of the manufacturing branch of Fenyi Conch Cement Co., Ltd., the company's cement production line with a daily output of 4500 tons is stepping up construction.

It is understood that in November 2023, the Jiangxi Office of Industry and Information Technology issued the announcement on the production capacity of Fenyi Conch Cement Co., Ltd. with a daily output of 4500 tons of cement clinker, saying that Fenyi Conch Cement Co., Ltd. intends to implement the overall relocation and technical renovation project of cement clinker production line from the city to the park, and will build a 4500t/d clinker production line, which will be built in the city. Withdraw from the company's original 2500t/d and 2000t/d clinker production lines. The project is planned to be ignited in June 2025. Commencement of

4000t/d clinker project of

Shandong Lianhe Wangqi Cement Co., Ltd. On February 26, the technical transformation project of 4000t/d new dry process cement clinker production line of Shandong Lianhe Wangqi Cement Co., Ltd. was commenced.

According to the release of Shandong Industry and Information Technology Office, The capacity replacement project of the 4000t/d clinker project of Shandong Lianhe Wangqi Cement Co., Ltd. is as follows:

Jinlei Southern Cement Green Building Material Industrial Park is expected to be completed and put into operation

in June. On February 20, 80% of the overall progress of the project was completed. Now it has entered the installation of main equipment and related commissioning work in an all-round way, and all construction units are making every effort to grasp the progress to ensure that the project will be put into operation on schedule in June this year.

It is reported that the project is located in Xinghong Village and Renli Village, Dongjiang Street, Chenzhou City, Hunan Province, with a planned land area of about 3000 mu. A new 4900t/d clinker new dry process cement production line will be built, with a designed clinker production capacity of 1.55 million tons per year and a cement production capacity of 2.4 million tons per year. After the project is completed and put into operation, the annual output value will exceed 1 billion yuan, which will become an innovative demonstration enterprise for sustainable development of traditional basic industrial manufacturing industry in Chenzhou, and will promote the rapid development of Zixing logistics industry and the comprehensive utilization of solid waste resources in surrounding enterprises. The civil engineering of the 4600t/d clinker project of

Real Madrid Cement has come to an end

. According to the report of Jiaoling County People's Government, the civil engineering has come to an end in the construction site of the first phase supporting project of the new dry process cement clinker production line of Real Madrid Cement.

Real Madrid Cement 4600t/d New Dry Process Cement Clinker Production Line and Waste Heat Power Generation Technical Transformation Project is to upgrade the original 2500t/d New Dry Process Clinker Production Line to 4600t/d New Dry Process Clinker Production Line by using the existing raw material and raw coal treatment system and the second-generation intelligent new dry process pre-decomposition production process. It is equipped with 9 MW pure low-temperature waste heat power generation unit. Announcement

of Environmental Impact Assessment of 9000t/d Clinker Project

of Jinfeng Group On January 26, the People's Government of Liyang City, Jiangsu Province issued the announcement of the approval of the environmental impact assessment document of Qianfeng Cement Construction Project. Basic information of

the project: Jinfeng Group plans to purchase Φ6.0 m, roller press, cement mill, roller vertical mill (cement), preheater, coal mill, generator, waste heat boiler and other equipment in the rotary kiln by eliminating the existing 2000 tons/day cement production line. A 9000-ton/day intelligent second-generation new dry-process cement demonstration production line will be built at the original site, with a total investment of about 3.3 billion yuan. Liyang Qianfeng Cement Co., Ltd. will be responsible for the construction and operation. The construction site is in the plant area of Jinfeng Cement Group, Green Building Material Industrial Park, Shezhu Pilot Area.

Cement industry has serious overcapacity, the impact of peak staggering production on the supply side has declined significantly, the "competition and cooperation relationship" formed over the years has broken down, and the pressure of industry operation has doubled. On March 28-29, China Cement Network will hold the " 13th China Cement Industry Summit and TOP100 Award Ceremony " in Hangzhou, during which awards will be given to top 100 cement and supplier enterprises, and experts and scholars will be invited. China Railway and other construction units jointly discuss the new development trend of the cement industry in the future, and work together to create the future!

All can be viewed after purchase
Correlation

Etuoke Banner Yongheng Cement Co., Ltd. was established on July 29, 2009, with its registered address located in the south of Jinghua Oxygen Plant, Qipanjing Industrial Park, Qipanjing Town, Etuoke Banner, Ordos City, Inner Mongolia Autonomous Region, and its legal representative is Wu Yongping. Its business scope includes licensed business items: production and sales of cement. General business items: sales of coal gangue, fly ash, clinker, limestone, granulated slag and gypsum.