Recently, Tianshui Tianxiang Cement Waste Heat Power Generation Project, contracted by Sinoma Energy Conservation, has been successfully connected to the grid. The project signed a contract on July 19, 2022, started construction on September 3, 2022, completed steam blowing on May 24, 2023, and realized grid-connected power generation on June 30, 2023.
Sinoma Energy Conservation Project Department carefully plans the work arrangement of each stage to ensure that the project generates electricity on schedule. In the early preparation stage of the project, the project department actively coordinates all departments to complete the basic design and procurement work in time; after the commencement of Tianshui area into the rainy season, the project department fully organizes the construction unit, supervision unit and the owner to strengthen cooperation, overcome difficulties together and ensure the construction progress; Entering the installation stage, all members of the project department overcome the difficulties of the epidemic, stick to the construction site, work overtime, one person on multiple posts, and ensure that the project reaches the project nodes on schedule as agreed in the contract. After the
project is connected to the grid for power generation, it is estimated that the annual average power generation will be about 3.68 × 10 ^ 7 kwh, the annual standard coal 10776 will be saved by tons, and the carbon dioxide emission will be reduced by about.5 tons 29876, which will make a positive contribution to the realization of the "double carbon" goal while improving the economic efficiency of enterprises.