China Minsheng Bank CBD Head Office Building Project, located in Block Z4 of the CBD core area of Chaoyang District, Beijing, is one of the key construction projects of the CBD core area of Chaoyang District, Beijing and a key project of Beijing. The land area is 10030 square meters, the total building area is 195,000 square meters, the building height is 140 meters, 26 floors above ground and 6 floors underground, belonging to the super high-rise financial headquarters office building. The project
is expected to be completed in 2025. After completion, it will become the global center, functional management center and brand center of Minsheng Bank.
After 82 hours of continuous construction, on the morning of March 14, the Minsheng Bank of China project, located in the Z4 block of Beijing CBD core area, which was constructed by the China Construction Third Engineering Bureau, completed the floor pouring at one time. This pouring will lay a solid foundation for the next construction of the project, and also open the prelude to the construction of the main structure of the project. In the row upon row of tall buildings in the CBD core area of
Beijing, several large tower cranes are slowly waving their "long arms" to lift goods. After dozens of concrete tankers queued up to enter the construction area, the flowing concrete was transported to the foundation pit by the "division of labor and cooperation" of the sky pump, the ground pump and the spreader. After the final finishing work, the bottom plate pouring construction was completed 7 days ahead of the original plan. After the concrete curing period of the base slab, the project will carry out the construction of the underground structure.