Recently, Gansu Industry and Information Technology Office issued the "Announcement on Cancellation of the 2500t/d Cement Clinker Production Line Capacity Transfer Scheme of Linxia Conch Cement Co., Ltd.".
The content shows that, affected by the policy of "double control of energy consumption" in Guangxi Zhuang Autonomous Region (capacity transferee), Xing'an Conch Cement Co., Ltd. (Capacity transferee) can not accept the transferred capacity, and the 2500t/d cement clinker production line capacity transfer scheme of Linxia Conch Cement Co., Ltd. will be cancelled.
According to the previous release of Gansu Industry and Information Technology Department, the above production line replacement plan is as follows:
According to Guilin Publishing Office, the signing ceremony of the 17th China-ASEAN Expo was held in Guangxi on November 27, 2020. On that day, the Guilin delegation signed 49 projects with a total amount of 128.505 billion yuan. Including the project of Xingan Conch Phase III 5000t/d new dry process cement clinker production line with an investment of 1.5 billion yuan.
It is understood that Guangxi has been required to rectify by the Central Environmental Protection Supervision Group because of the inadequate management and control of the "two high" projects. According to the Ministry of Ecology and Environment, during the "14th Five-Year Plan" period, the impulse to launch the "two high" projects in Guangxi is still strong. The production capacity of some energy-intensive industries continued to expand. In 2020, the output of flat glass, ten kinds of non-ferrous metals and electrolytic aluminium in the whole region was 4.3 times, 2.6 times and 3.8 times that in 2015, respectively. In recent years, Guangxi has replaced cement production capacity from 18 provinces in China, and the cement clinker production capacity of 12 projects under construction has reached 17.34 million tons, which is 2.9 times the increment of the 13th Five-Year Plan. The Guangxi Office of Industry and Information Technology recently released the completion of the rectification task, saying that the rectification measures have been completed and continued to advance due to the inadequate management and control of the "two high" projects.
It is understood that in recent years, a number of cement clinker production capacity replacement projects have been withdrawn, according to public information, in addition to the project can not be landed, the reasons for the withdrawal include friendly consultation, the project can not be constructed on schedule..
On
December 15, the Jiangsu Provincial Department of Industry and Information Technology issued the "Central Eco-environmental Protection Supervision and Rectification Announcement", which showed that due to the lax implementation of the cement capacity replacement policy, the capacity replacement scheme of the cement clinker production line of Liyang Qianfeng Cement Co., Ltd. was cancelled and announced on the website of the Provincial Department of Industry and Information Technology. The cement clinker production capacity of Liyang Dongfang Cement Co., Ltd. is no longer used as the exit capacity source of the relevant capacity replacement project.
Liyang Qianfeng Cement Co., Ltd. has reformulated the project capacity replacement plan, and the project shall not start construction before the capacity replacement is in place.
On January 9, Shaanxi Provincial Department of Industry and Information Technology issued a notice on the cancellation of the production capacity transfer plan of Fengxian Shengwei Building Materials Co., Ltd. for the production line with a daily output of 1500 tons (special cement clinker).
The announcement shows that after friendly consultation among Fengxian Shengwei Building Materials Co., Ltd., Yichun Hongshi Cement Co., Ltd. and Shangrao Hongshi Building Materials Co., Ltd. The announcement of Fengxian Shengwei Building Materials Co., Ltd. on the production capacity transfer scheme of 1500 tons per day (special cement clinker) production line (website announcement of April 26, 2022) will no longer be implemented, according to the Ministry of Industry and Information Technology's "Measures for the Implementation of Capacity Replacement in Cement Glass Industry" (Ministry of Industry and Information Technology's original [2021] 80). The announcement of the production capacity transfer plan of Fengxian Shengwei Building Materials Co., Ltd. is hereby revoked.
On January 6, the Shanxi Provincial Office of Industry and Information Technology issued the Announcement on the Cancellation of the Capacity Replacement Plan of Yuci Cement Co., Ltd. of Zhihai Enterprise Group. According to
the announcement, according to the requirements of the Notice of the Ministry of Industry and Information Technology on Issuing the Implementation Measures for Capacity Replacement in Cement and Glass Industry (Ministry of Industry and Information Technology No.2021), the announcement on the capacity of Yuci Cement Co., Ltd. of Zhihai Group has been revoked upon the application of Jinzhong Industry and Information Bureau. On November 24,
2022, the Guizhou Office of Industry and Information Technology issued the Announcement
on the Cancellation of the Capacity Replacement Scheme for the Construction Project of the Clinker Cement Production Line of Guiyang Southwest Environmental Protection Building Materials Co., Ltd. Our office has made a public announcement on the "reduction and replacement" scheme of the clinker cement production line construction project of Guiyang Southwest Environmental Protection Building Materials Co., Ltd. Due to the project can not be constructed on schedule, after the application of Guiyang Southwest Environmental Protection Building Materials Co., Ltd. and the county and municipal industry and information departments, the "reduction and replacement" scheme of the clinker cement production line construction project of Guiyang Southwest Environmental Protection Building Materials Co., Ltd. is hereby cancelled.