Investment exceeds 4.2 billion yuan! Seven sand and gravel projects in Zongyang, Anhui signed/started/put into operation this year

2023-07-11 09:25:36

There are seven sand and gravel related projects (including one sand and gravel corridor transportation project), with a total investment of 4.254 billion yuan. Among them, there are two start-up projects, four contracted projects and one key project, with a total annual capacity of 52.4 million tons.

Recently, the People's Government of Zongyang County, Tongling City, Anhui Province issued a list of 2023 key double-recruitment and double-attraction projects for county leaders. There are 69 key projects in the list, with a total investment of 73.2 billion yuan. There are seven sand and gravel related projects (including one sand and gravel corridor transportation project), with a total investment of 4.254 billion yuan. Among them, there are two start-up projects, four contracted projects and one key project, with a total annual capacity of 52.4 million tons.

The project is invested and constructed by Zongyang Southern Materials Co., Ltd., with an investment of 577 million yuan, to build a primary aggregate production line with an annual output of 20 million tons, as well as necessary auxiliary production and living facilities.

At present, the main body of the office and working and living facilities, the road of the unloading platform site, the retaining wall and the pile foundation of the platform have been basically completed, and the greening and decoration work is being carried out. The main body of the project is expected to start this year.

2

Zongyang Nanfang Material Production Line

with an annual output of 15.6 million tons of fine machine-made sand and gravel aggregate is invested and constructed by Zongyang Nanfang Material Co., Ltd. with an investment of 454 million yuan. A production line with an annual output of 15.6 million tons of fine machine-made sand and gravel aggregates will be built from the primary aggregate storage area of the wharf to the sand and gravel aggregates loading and transfer station.

At present, the project is carrying out the work of land approval, requisition and relocation, and preparation for the use of shoreline. Construction is expected to start within this year.

3

Zongyang Southern Materials Green Transportation Project

The project is invested and constructed by Zongyang Southern Materials Co., Ltd. with an investment of 796 million yuan to construct a belt conveyor corridor project of about 22.5 kilometers from the primary aggregate project plant to the production plant.

At present, the project has completed the signing of land requisition and lease agreements for 1 # and 2 # tunnel entrances, and the related work for 3 , 4 # and 5 # tunnel entrances is progressing in an orderly manner. Construction is expected to start within this year.

4

Duanyaoling Machine-made Sand Project

with an Annual Output of 3 Million Tons Located in Qianpu Village, Changshan Village, Huanggang Village and Jiangjun Village, Qianpu Town, Zongyang County, the project is invested and constructed by Yongsheng Building Materials Co., Ltd. of Zongyang County with an investment of 300 million yuan.

The project covers an area of 80 mu, including a new processing area of about 20 mu, a screening workshop and a finished product silo of about 60 mu, and two sets of new machine-made sand equipment need to be purchased. The two workshops adopt advanced production modes of green building materials such as intelligence, environmental protection, video surveillance and automation system. It is estimated that the annual output of machine-made sand is 3 million tons, the annual output value is about 200 million yuan, and the annual tax revenue is about 15 million yuan.

At present, the project agreement has been signed, the relevant procedures are being processed, and construction is expected to start in July.

The project is located in Xiangwan Group, Xiushan Village, Jinshe Town, Zongyang County, and is invested and constructed by Tongling Zhewei Building Materials Co., Ltd. with an investment of 200 million yuan.

The project uses the original quarry (covering an area of about 0.23 hectares), plans to build a new standardized workshop (covering an area of about 6000 square meters, with a building area of about 20000 square meters) for the construction of the comprehensive utilization project of solid waste in the quarry of Xiushan Village, Jinshe Town, Zongyang County, and purchases production equipment such as crushers, sand washers and filter presses. After the completion of the project, the annual processing capacity of 2 million tons of waste basalt ore in the mining area can be reached, and the annual production capacity of 2 million tons of machine-made sand and gravel can be increased.

At present, the construction of the external highway of the project has been completed, the leveling construction of the plant plot is under way, and the small crusher and other equipment have entered the site and are expected to be put into operation within this year.

The project is located in Qianpu Village and Changshan Village of Qianpu Town, and is invested and constructed by Yulong Stone Co., Ltd. of Zongyang County, with an investment of 210 million yuan.

The project covers an area of about 72 mu, with a new processing workshop of 22 mu, a screening workshop, a finished product silo of about 50 mu and a 1.5 km belt corridor. It adopts advanced production modes of green building materials such as intelligent control system, environmental protection dust removal and suppression system, and can produce 2 million tons of machine-made sand annually after putting into operation.

At present, the project is carrying out the road leading to the main mining area, involving the collection and survey of mountain fields and related coordination work. The land in the processing area has been basically leveled, and the main mining area is planned to be exploited. The main body is expected to be constructed within the year.

The project is invested and constructed by Anhui Xuanwu New Materials Co., Ltd., with an investment of 1.717 billion yuan. It is planned to develop and utilize the andesite and basalt for the construction of screw tip, with an annual mining scale of 9.8 million tons.

At present, contracts for land use, forest use, environmental impact assessment and other aspects required for mining are being signed in April of the second quarter.

All can be viewed after purchase
Correlation

There are seven sand and gravel related projects (including one sand and gravel corridor transportation project), with a total investment of 4.254 billion yuan. Among them, there are two start-up projects, four contracted projects and one key project, with a total annual capacity of 52.4 million tons.

2023-07-11 09:25:36

The Statistical Table of Port Coal Prices shows the changes of coal prices in domestic multi-regional ports from September 4 to September 11, 2025. Overall, some port prices have declined, some remain stable, and there is a small increase. The price of general bituminous coal with a calorific value of 5,000 at Zhujiang Power Terminal has changed significantly, with a relatively large decrease; the price of some coal types at Rugao Port, Jingjiang Yingli Port, Jiangyin Port and other ports has changed slightly, with a value of 0, and the price has remained stable.