Land and water combined transport "building blocks"

2023-03-17 09:46:43

At the construction site of Zishui Bridge at Malukou, the seventh contract section of Guanxin Expressway, more than 40 construction and management personnel and several mechanical equipment are carrying out the erection of the main bridge deck.

After the

The Waking of Insects, the land of Sanxiang gradually warmed up. At the construction site of Zishui Bridge at Malukou, the seventh contract section of Guanxin Expressway, more than 40 construction and management personnel and several mechanical equipment are carrying out the erection of the main bridge deck. Overlooking the Zijiang River under the bridge, a small boat carrying three "passengers"-two concrete tankers and a stone truck, came slowly towards the bridge.

"Land and water transport is the normal construction of the bridge, and the biggest difficulty faced by the construction is the water transport capacity." Liang Yipeng, deputy chief engineer of the seventh contract section, said that because the Zishui Bridge at Malukou is located in Xuefeng Lake National Wetland Park and is affected by Zhexi Dam, building materials can not be transported in large quantities by kiloton ships.

Malukou Zishui Bridge, with a total length of 1187 meters, is a key control project of Guanxin Expressway and the longest span steel-concrete composite girder cable-stayed bridge in Hunan Province. The main bridge is expected to be closed by the end of July. Liang Yipeng touched the ground with his feet: "The bridge deck we see now, under normal construction environment, the steel beam can be prefabricated and assembled first, and then transported to the bridge construction site by ship for integral hoisting.". But here, the problem is not hoisting, but transportation. If the size and weight of the pre-assembled finished products are too large, the ship can not be loaded, but can not be transported to the site by water.

In this case, the project department changed its strategy and adopted on-site assembly technology for the superstructure of the bridge. For a section of steel-concrete composite beam, only the segmented steel beam and prefabricated bridge deck need to be transported by ship to the site like "building blocks". The seventh contract section is equipped with two cargo ships, only relying on these "brothers", the builders use the way of "building blocks" to simplify the task. Huangshajie Tunnel of the eighth contract section, about 2 kilometers

away from Zishui Bridge at Malukou, is another control project of Guanxin Expressway. Outside the entrance of the tunnel, a staff member skillfully operated the computer, showing several photos of the tunnel on the screen, with several sets of analysis data attached to one side of the photos. "This is a picture taken by front-line workers in the tunnel ten seconds ago." The staff pointed to the screen and said, "We take photos and upload the system through the front, and the background converts the two-dimensional image into three-dimensional data, and generates the effect map, which can better guide the tunnel excavation work." There are 11 fault fracture zones in the tunnel site

of Huangshajie Tunnel, with complex geological structure and local water gushing and water inrush. "Tunnel construction is most afraid of complex geological conditions." Yang Jie, the technical director of the project, said that after repeated research and tests, the technicians effectively controlled the rock mass in the fracture zone in advance by means of advanced geological exploration, combination of long and short bolts and advanced small pipes.

Guanzhuang-Xinhua Expressway is an important part of Hohhot-Beihai Expressway, with a total length of nearly 77 kilometers. As one of the opening projects in Hunan this year, by the end of February, 93% of the bridge works of Guanxin Expressway had been completed, 97.2% of the tunnel works had been completed, and 30% of the pavement subbase had been completed.


All can be viewed after purchase
Correlation

At the construction site of Zishui Bridge at Malukou, the seventh contract section of Guanxin Expressway, more than 40 construction and management personnel and several mechanical equipment are carrying out the erection of the main bridge deck.

2023-03-17 09:46:43

Grinding technology and equipment of wet slag discharge vertical mill; key technology of Bayer process red mud quality control to produce matrix composite materials; key technology and equipment of comprehensive utilization of fly ash quality improvement and carbon reduction; technology of solid waste resource utilization coupled with carbon dioxide capture and storage utilization (CCUS); remanufacturing technology of wear-resistant parts of mechanical equipment; remanufacturing technology of permanent magnetization of old motors; The green remanufacturing technology of high-precision and long-life gearboxes has been listed in the Catalogue of Advanced and Applicable Technology and Equipment for Comprehensive Utilization of National Industrial Resources (2025 edition).