25.2 meters! The deepest civil construction foundation pit in Fujian Province, "chute + branch trough" pouring mass concrete!

2023-07-04 13:37:21

Xiamen Lvfa New Times Square Block B Project completed the first raft pouring.

Recently, With the completion

of the last concrete pouring, Xiamen Lvfa New Times Square Block B Project

has completed the first raft pouring

and formally entered the construction stage

of the main structure, which is the first successful application

of "chute + branch trough" pouring in Xiamen. The concrete project

is 25.2 meters! The deepest civil construction foundation pit

in Fujian Province Xiamen Lvfa New Times Square Plot B Project

has a construction area of 122,000 square meters

, a construction height of 192 meters

, and a foundation pit excavation depth of 25.2 meters

, which is the deepest civil construction foundation pit in Fujian Province. L0 UNK1 2 is positioned as an international high-end luxury five-star hotel 0 HTML 0 UNK1 3 will be built into a new landmark of cities on both sides of the Taiwan Strait 0 HTML 0 UNK1 4 is the raft of the main building of Tower B 0 HTML 0 UNK1 5 is about 63 meters long. Width about 69m 0 HTML0 UNK1 6 Raft thickness 2.7m 0 HTML0 UNK1 7 Concrete pouring about 5700 cubic meters 0 HTML0 UNK1 8 This pouring lasted 22 hours 0 HTML0 UNK1 More than 970 concrete trucks worked continuously 0 HTML0 UNK2 0 New breakthrough! First application in Xiamen construction field 0 HTML 0 UNK2 1 The project is located in the core of Xiamen City 0 HTML 0 UNK2 2 The scope of the foundation pit is the scope of the red line 0 HTML 0 UNK2 3 There is no construction road on the site 0 HTML 0 UNK2 4 And four internal supports are set in the pit 0 HTML 0 UNK2 5 The traditional pouring method of "sky pump + ground pump" 0 H TML0 UNK2 6 can not meet the construction requirements 0 HTML0 UNK2 7 After comparison, the project team decided to adopt 0 HTML0 UNK2 8 The pouring scheme of "chute + branch channel" independently designed by the company 0 HTML0 UNK2 9 has the characteristics of low carbon, environmental protection, High efficiency and other features 0 HTML 0 UNK3 0 2 sets of elephant trunks are arranged during pouring 0 HTML 0 UNK3 116 tributary troughs, 2 truck-mounted pumps 0 HTML 0 UNK3 2 Pouring volume per hour exceeds 360 cubic meters 0 HTML 0 UNK3 3 Expected to reduce fuel consumption by 1710 liters or electricity consumption by 7530 degrees 0 HTML 0 UNK3 4 Reduce carbon emissions by 7.5 tons 0 HTML 0 UNK3 5 Project team scientific organization, Precise deployment 0 HTML 0 UNK3 6 Comprehensive planning and coordination of surrounding sites and municipal road resources 0 HTML 0 UNK3 7 Guarantee the smooth progress of pouring 0 HTML 0 UNK3 8 Become the first successful application of Xiamen 0 HTML 0 UNK3 9 "chute + branch channel" pouring mass concrete project 0 HTML 0 UNK4 0 To efficiently build 0HTML0 UNK4 1 and sound the charge of Haixi construction 0HTML0 UNK4 2

All can be viewed after purchase
Correlation

Xiamen Lvfa New Times Square Block B Project completed the first raft pouring.

2023-07-04 13:37:21

On September 5, Chairman Shao Jun of China Cement Network and his delegation visited Ningde Conch Cement Co., Ltd. and were warmly received by General Manager Hong Xianli and others. The two sides exchanged views on the situation of Fujian cement market.