"Staged" 100-man wheel battle! 30 hours, 1200m ³ concrete pouring is fully completed!

2023-03-06 15:55:33

A total of 1200 m ³ of concrete was poured, 100 person-times were invested, and the peak value of pouring in the sprint stage reached 50 m ³/H.

A few days ago, the pump layer of the new Doumen sluice station reconstruction project successfully completed 30 hours of continuous concrete pouring, laying a solid foundation for the completion of the follow-up flood control and drainage node tasks, and once again set off a construction boom for the main body of the pump sluice station.

It is understood that a total of 1200m ³ of concrete has been poured, 100 people have been invested, and the peak value of pouring in the sprint stage has reached 50m ³/H. Faced with the characteristics of large volume and long time of concrete pouring, in order to ensure the quality of "soft stubble" of concrete, avoid penetrating cracks, effectively deal with the problems of hydration heat, heat preservation and cooling, and reduce the impact of large vehicles on nearby villages and towns, the District Forestry and Water Bureau intervened in advance to guide, and Yuhang Linshui Investment Company organized all participating units. Formulate a feasible, accurate and efficient construction plan. Before

the concrete pouring, Yuhang Linshui Investment Company organized the EPC General Contracting Project Department and the Supervision Department to hold the first concrete pouring coordination meeting, and set up a large volume concrete pouring command working group to clarify the responsibilities of all participants in the pouring. In-depth management of on-site command, station communication, supplies allocation, safety supervision, technical guidance, quality control, test sampling, vehicle scheduling, road coordination, emergency response, logistical support and other aspects. The whole staff participated in the

concrete pouring operation, the internal and external personnel cooperated, the responsible person stuck to the site for 30 hours in the whole process, and the construction workers worked in three shifts to ensure that each post was dedicated and responsible for 24 hours, giving full play to the vanguard and exemplary role of Party members, and successfully completed the mass concrete pouring task.

All can be viewed after purchase
Correlation

A total of 1200 m ³ of concrete was poured, 100 person-times were invested, and the peak value of pouring in the sprint stage reached 50 m ³/H.

2023-03-06 15:55:33

On September 9, Huaxin held a semi-annual performance conference in Wuhan in 2025. President Li Yeqing, Vice President and Chief Financial Officer Chen Qian, Vice President and Secretary of the Board of Directors Ye Jiaxing attended the event as exchange guests.