Anhui Releases List of Key Projects in 2023, 30 + Sandstone Projects on the List

2023-02-28 09:39:34

There are about 34 sand and gravel related projects in the key projects in 2023, with a total annual production capacity of about 240 million tons and a total investment of over 30 billion yuan.

Recently, the Anhui Provincial People's Government issued a list of key projects in 2023 (the first batch), with a total of about 9600 key projects in the first batch. Among the key projects in 2023, there are about 34 sand and gravel related projects, with a total annual production capacity of about 2. Among them, the largest project is the Hengshan Mining Area in Guichi District and the peripheral cement limestone mine project. Total investment 91.

The list of key projects involving sand and gravel projects is as follows:

, Project Name: Xiaoxian Conch Green Building Materials (Phase I) Project

Total Investment: 10. Annual output of 5 million tons of high-quality machine-made sand aggregate and 1.2 million cubic meters of commercial concrete.

3. Project Name: Basalt New Building Materials Phase I Annual Output of 3 Million Tons of Basalt Building Aggregate and 1 Million Tons of Machine-made Sand Processing Project

Total Investment: 500 million yuan

Construction Content and Scale: The main project is to build a production line of fine aggregate and a production line of ordinary aggregate. In addition, production auxiliary room, sewage treatment and reclaimed water reuse, wastewater treatment (filter pressing workshop), fire water pool and fire pump room, mechanical and electrical maintenance, power distribution room, belt corridor and transfer, guard room, mud stacking shed, semi-finished material stack (general material), semi-finished material stack (fine material) and finished aggregate warehouse shall be provided. It can reach the annual production capacity of 3 million tons of basalt building aggregate and 1 million tons of machine-made sand.

4. Project Name: 9 Million t/a Open-pit Mining Project

of Limestone Mine for Building Stones in Laoheishan, Dingyuan County Total Investment: 30875.

Screenshot

of the List of Sand and Gravel Projects 5. Project Name: Tuff Mine for Building Stones in Shengrenshan Mining Area, Huoshan County

Total Investment: 16. Mine Service Life: 21.6

, Project Name: Bowang District Conch Green Building Material Industrial Base Phase I Project

Total Investment: 5 billion

Construction Content and Scale: Construct Conch Green Building Material Industrial Base and build a rural revitalization demonstration area integrating modern agriculture, tourism and recreation. The annual output of intelligent aggregate machine-made sand, prefabricated building and brick-making green building materials is 9.6 million tons.

7. Project name: Maanshan Nanfang Materials Co., Ltd. Project

with an annual output of 15 million tons of green, ecological and environmental protection high-quality aggregates Total investment: 3.9 billion yuan

Construction content and scale: Total construction area 19. The annual throughput of the supporting construction is 15 million tons of wharf and other ancillary projects. After the completion of the project, the annual output will be 15 million tons of green ecological and environmental protection high-quality aggregate.

8. Project name: Hexian County, with an annual output of 7 million tons of building materials and stones

. Total investment: 1551.87 million yuan

. Construction content and scale: The project is divided into two phases of mining, using automobile transportation. The main construction contents include open pit, mine road, dump, mine industrial site, crushing station, etc. The scale of the crushing station is suitable for the scale of the mine. After the completion of the project, it can produce 7 million tons of aggregate annually.

9. Project Name: Xuanzhou Qingfengshan-Zaozigou Limestone Development Project

for Building Stones Construction Content and Scale: Mining Area Scope 1376.

Project Name: Ningguo Wayaopu Limestone Mine Development Project

for Building Stones Total Investment: 1 billion

Construction Content and Scale: The project is planned to cover an area of 545 mu, with a total construction area of 80000 square meters, and will be constructed in two phases. Purchase various feeders, crushers, belt conveyors and other equipment to process 8 million tons of sand and gravel annually in the first phase and 7 million tons in the second phase. Screenshot

of Sandstone Project List 11. Project Name: Jinlei Limestone Mine Development Project

Total Investment: 1.314 billion yuan

Construction Scale: Annual Output of 9.6 million tons

12. Project Name: Conch 13 Million Tons/Year Flux Limestone Comprehensive Utilization Project

Total Investment: 600 million yuan

Construction Content and Scale: Including mine crusher, 5.13

, Project Name: Annual Output of 20 Million Tons of Fine Machine-made Sand and Gravel Aggregate Project

Total Investment: 3.5 billion yuan

Construction Content and Scale: The construction of Huanggongshan Project includes four parts: mining area, ore processing area, long belt conveyor corridor and wharf storage area. Annual output of 20 million tons of high-quality machine-made sand and gravel aggregate.

14. Project Name: Luosijian Building Stone Andesite and Basalt Mine Project

in Zongyang County Construction Scale: Annual Output of 9.8 million tons

15. Project Name: Annual Output of 40 Million Tons of Cement Limestone Mine in Hengshan Mining Area and Periphery of Guichi District

Total Investment:

91.16, Project Name: Dongzhi County Huafeng Mining Area Deep and Peripheral Construction Dolomite Limestone Mine 9 Million Tons/Year Construction Project

Construction Scale: Annual Output of 9 Million Tons of

Sandstone Project List Screenshot

17, Project Name: Aggregate Processing EPC Project

with Annual Output of 9 Million Tons of Limestone Mine for Building Stones in Matanghu, Quanjiao, Anhui Province Total Investment:

4.18. Project Name: Aggregate Processing Project

of Limestone Mine for Building Stones in Laoheishan, Dingyuan County, Anhui Province Construction Scale: Annual Output of 9 Million Tons.

19. Project Name: Hexian Hengshan Mining Project

with Annual Output of 3 Million Tons of Machine-made Sand Construction Scale: Annual Output of 3 Million Tons.

20. Project Name: 2 Million Tons Annual Stone Processing Project of Wuhu Jiusheng Building Materials Co., Ltd. Environmental

Construction Scale: 2 million tons annual output.

, Project Name: Yulong Building Stone Tuff Ore Processing Project

Total Investment:

1.23, Project Name: Qianshan Qianrun Sandstone Building Materials Co., Ltd. Building Materials Comprehensive Industrial Park (Phase I) Project

Construction Scale: Annual processing of 1.8 million tons of machine-made sand.

All can be viewed after purchase
Correlation

There are about 34 sand and gravel related projects in the key projects in 2023, with a total annual production capacity of about 240 million tons and a total investment of over 30 billion yuan.

2023-02-28 09:39:34

The title is "Cement and Clinker Inventory Statistics". The statistics include the data of storage location (%), year-on-year storage location (percentage point) and month-on-month storage location (percentage point) of clinker and cement in different regions of the country on July 25. In terms of clinker, the data of different regions are different. The change value of year-on-year storage location in East China is considerable, and the change value of month-on-month storage location in Northeast China is relatively obvious. In terms of cement, the change value of year-on-year storage location in Southwest China is more prominent, and the change value of month-on-month storage location in Central and South China is relatively small.