On October 7, the rotary kiln of Suzhou Sinoma Uzbekistan Andiyan 6000 t/d clinker cement production line project was successfully closed.
This project is located in the hinterland of Central Asia, with long distance of cross-border highway transportation and great difficulty in logistics of large equipment. After the arrival of super-large equipment such as kiln barrel and tyre, the project department responded quickly, formulated and improved the hoisting plan, carefully optimized the division of labor, simulated and deduced the hoisting process, and did a good job of safety and technical disclosure in an all-round way. In the process of hoisting assembly, the sudden failure of the external line led to the power outage of the whole site, and the field operators quickly started the contingency plan and started the standby power supply, which effectively guaranteed the welding assembly of the kiln barrel, and finally completed the closure of the kiln barrel successfully in three days.
It is understood that the Andijan project is invested and constructed by China West Cement Group Co., Ltd. with a total investment of 250 million US dollars and a construction period of 14 months. It adopts the world's most advanced new second-generation dry cement production line technology and equipment, and its informatization, intellectualization and various technical indicators have reached the international advanced level. After the completion of the
project, it will provide 2.2 million tons of high-quality cement for Andijan and its surrounding areas every year, with an annual profit and tax of about 200 billion sum, and promote the rapid development of local related industries, contributing to the economic and social development of Andijan.