On February 15, the Department of Industry and Information Technology of Xinjiang Uygur Autonomous Region issued a notice on the adjustment of peak staggering production time for Xinjiang cement enterprises in 2022-2023 (the first batch). The
documents are as follows:
The documents show that Kuqa Hongshi Cement Co., Ltd. and Korla Luyue Sanchuan Building Materials Co., Ltd. will open kilns from February 15 to March 15 (29 days in total) during the peak staggering period. Kuqa Hongshi Cement Co., Ltd. will shut down the kiln from September 15 to October 13 (29 days in total) during the off-peak period, and Korla Luyue Sanchuan Building Materials Co., Ltd. will shut down the kiln from September 1 to September 29 (29 days in total) during the off-peak period.