The monthly concrete pouring volume of the powerhouse of Maerdang Hydropower Station has reached a new high

2023-06-06 10:25:17

The concrete pouring volume of the powerhouse of Maerdang Hydropower Station reached 84600 cubic meters in May, setting the highest monthly record since the concrete pouring of the powerhouse project.

On May 31, the concrete pouring volume of the powerhouse of Maerdang Hydropower Station reached 84,600 cubic meters in May, setting the highest monthly record since the concrete pouring of the powerhouse project.

The picture shows the image

of the construction of the turbine floor of Unit 5 of the main powerhouse. 2023 is the peak and key year for the concrete pouring of the powerhouse of Maerdang Hydropower Station. 510,000 cubic meters of concrete need to be poured throughout the year. In October, there will be important nodes such as sluice impoundment. The monthly concrete pouring volume of the plant has reached a record high, which fully demonstrates the company's technical strength in mass concrete pouring and lays a solid foundation for subsequent concrete construction. Since

March, the construction of the main project of Maerdang Hydropower Station has been in full swing, and the construction site is a hot scene, with roaring machines, busy figures and concrete tankers shuttling back and forth. In order to ensure the high-speed progress of the project construction and achieve the goal of impoundment on schedule, the company carefully studied the difficult construction situation it was facing, convened a special meeting to deploy construction tasks, and organized all parties involved in the construction to start with optimizing the construction scheme, strengthening the allocation of resources and improving the construction layout, so as to effectively enhance the intensity and efficiency of concrete production, transportation and pouring. The monthly pouring volume was overfulfilled.

In the next step, Maerdang Company will continue to scientifically formulate the construction plan, decompose the construction plan into monthly, weekly, daily and shift, comprehensively refine and materialize the construction measures, and guarantee the day, week and month by shift, so as to lay a solid foundation for the impoundment of the sluice gate at the end of October 2023 and the power generation of the first unit at the end of March 2024. (Wang Zhengxiong)

All can be viewed after purchase
Correlation

The concrete pouring volume of the powerhouse of Maerdang Hydropower Station reached 84600 cubic meters in May, setting the highest monthly record since the concrete pouring of the powerhouse project.

2023-06-06 10:25:17

Located in Dianbai District, Maoming City, Guangdong Province, this project is an ordinary highway project with a total length of about 18.914 kilometers, starting from the intersection of Fushanling Avenue (proposed) and ending at the intersection of the South Extension Line of the Western Express Line (proposed), crossing Danchang Town, Shuidong Town, Qijing Town and Xiaoliang Town along the line, covering an area of about 1,213,150 square meters. The subgrade is 33m wide, with two-way 6 lanes, design speed of 80km/H, and asphalt concrete pavement; the total length of bridges along the line is 6,389.1m, with 19 bridges, including 2 super-large bridges (4,110.8m in total).