Recently, Hubei, Yunnan, Jiangxi and other places have released the peak staggering production plan of the cement industry in 2023, and the shutdown time in some areas has increased significantly compared with previous years.
The peak-staggering plan for each province is as follows:
Hubei: No less than 30-60 days
of production suspension Jiangxi: No less than 40 days
of production suspension in the first quarter Yunnan: Up to 150 days
of production suspension Fujian: No less than 65 days
of production suspension throughout the year Shandong: production will be suspended for up to 121 days (from November 15, 2022 to March 15, 2023)
Henan: production will be suspended for up to 121 days (from November 15, 2022 to March 15, 2023) Hebei: production will be suspended for up to 150 days (from the start of heating in 2022 to the start of heating in 2023) The day before the start of heating)
Hunan: stop production for 75-80 days (during the special protection period of air pollution prevention and control in 2022-2023)
Guangdong: 60 + 20 days for the whole year (from January 1 to April 30, 2023, the number of days of off-peak kiln shutdown is 40 + 10 days; From July 1 to September 30, 2023, 20 + 10 days of off-peak shutdown)
Guangxi: 130 days
of shutdown Shaanxi: 100 days of shutdown (December 1, 2022-March 10, 2023)
Ningxia: 120 days of shutdown (November 1, 2022-March 10, 2023)
Gansu: Stop production for 100 days (December 1, 2022-March 10, 2023)
Xinjiang: Stop production for 125-226 days (November 1, 2022-September 30, 2023)