On January 31, the commencement of major projects in the first quarter of Hubei Province was held. Huanggang simultaneously set up a branch venue at the site of Dabie Mountain Clean Power Supply Project to hold the commencement of major projects in the first quarter of the city. The Qichun Branch was held simultaneously through video links. Huanggang Municipal Government, relevant departments and leaders of relevant county and county governments participated. Hu Anyuan, Secretary of Qichun County Party Committee, participated in the activities at Qichun Branch and announced the start of a major project in the first quarter of Qichun County and the project of Shiguchong Green Building Material Base. Jian Shangyou, Party Secretary and General Manager of Central China Regional Headquarters of China Power Construction Group/Temporary Party Secretary and Chairman of Central China Investment Company, attended the event and delivered a speech at Qichun Branch. Li Ketao, Vice General Manager of Central China Regional Headquarters/Central China Investment Company, attended the event at Qichun Branch.
Jian Shangyou, on behalf of Central China Regional Headquarters/Central China Investment Company of China Electric Power Construction Group, thanked the local governments at all levels, such as Huanggang Municipal Committee and Municipal Government, Qichun County Committee and County Government, for their trust and support. He said that starting from the start of the project, he would give full play to the spirit of the central enterprises, give full play to the advantages of the integration of the whole industry chain of green building materials in China Electric Power Construction, and plan scientifically. Careful deployment, efficient linkage, speed up the construction progress, and strive to build Qichun Green Mine Project into a digital, intelligent, green industry benchmark and green model, to make due contributions to the high-quality economic and social development of Qichun County. Shiguchong Green Building Material Base Project in Qichun County,
Hubei Province, with a total investment of about 14 billion yuan, is mainly composed of mining engineering, sand and gravel processing system engineering, long rubber corridor transportation engineering, wharf and land yard engineering. With ecological, social and economic benefits, the project is expected to provide 70 million tons of green machine-made sand and gravel aggregates for cities in the middle and lower reaches of the Yangtze River every year, help Qichun County develop its economy, society and ecology with high quality, and accelerate the construction of Huanggang as a regional central city in eastern Hubei Province. Heads of relevant departments of
Central China Regional Headquarters/Central China Investment Company, China Electric Power Construction (Qichun) New Materials Co., Ltd., heads of project construction units and staff, totaling more than 50 people, participated in the activities.
According to the China Sandstone Association, the Shiguchong Green Building Material Base Project in Qichun County, Hubei Province is located at the junction of Liuhe, Lion and Qingshi Towns in Qichun County, with an area of 6179 mu, a total investment of about 14.3 billion yuan, a construction and operation period of 23 years, a resource reserve of about 1.25 billion tons, and an annual mining scale of 70 million tons. It is mainly composed of mining engineering, sand and gravel factory engineering, long rubber corridor engineering, wharf and land storage yard engineering, with a total annual throughput of 70 million tons.
The project plans to adopt the joint development and transportation scheme of highway and adit chute, with a total of three 8-meter-diameter chutes (two in the west ore section and one in the east ore section). The blasted ore is transported to the chute by truck, crushed by the underground crushing system, and transported to the side processing system of the mine by belt conveyor adit. The scheme has the advantages of short automobile transportation distance, mature technology, energy saving and consumption reduction, and large output. The
sand and gravel plant is arranged in a decentralized manner, consisting of a coarse crushing workshop, a semi-finished product storage yard, a medium crushing workshop and a mixture storage yard on the mine side. The mixture processing system is arranged 2km away from the southwest of the mining area, and the coarse crushing workshop is arranged underground. The finished product sand and stone plant consisting of the mixture storage yard at the wharf side, the finished product screening workshop, the fine crushing workshop, the sand making regulating material pile and the rod grinding (shaping) sand making workshop is arranged in the rear land area of Maoshan Wharf. All workshops are arranged on the ground. The two parts of sand and stone plants are connected by a long rubber corridor of 39.5 kilometers. The total length of the
long rubber corridor is about 39.5 kilometers, passing through five townships of Liuhe Town, Shizi Town, Zhulin Town, Hengche Town and Pengsi Town. The long rubber gallery is arranged in a single line. The gallery is about 6 meters wide. Considering the installation, overhaul, maintenance and other factors, the section covers a total area of 12 meters. The transported goods are gravel aggregate mixture with a particle size of less than 100 mm. The designed transport capacity is 15000 tons per hour, the designed belt width is 2400 mm, and the designed belt speed is 5.6 meters per second. The crossing points include rivers, highways, railways and other sensitive points.
The wharf is located at Chaoshuiji, Maoshan Operating Area, Pengsi Town. It is planned to construct eight 10000-ton bulk cargo export berths. The wharf structure is high-pile beam-slab structure. The length of the wharf shoreline is 1240 meters, equipped with 8 straight-line ship loaders of 4000 tons per hour, with an annual throughput capacity of 80.4 million tons per year for bulk cargo export, and the storage yard is designed for 7 days of inventory.
Qichun Shiguchong Green Building Material Base Project is the "vanguard" project of Chinese-style modernization development, and it is also an important strategic measure to actively build a green mining security system and promote the rapid development of local economy and society. It is of great significance and glorious mission to build this project well. After the completion of the
project, it will not only promote the coordinated development of Qichun County's economy, society and ecology with high quality, but also help Huanggang become an important growth pole of Hubei's high-quality development.