1. A new high! From January to August, the newly installed photovoltaic capacity in China exceeded 100 million kilowatts for the first time (click the title to view the full text)
. On September 19, the National Energy Administration released the "Statistics of the National Power Industry from January to August", which showed that the installed capacity of solar power from January to August was about 510 million kilowatts, an increase of 44.4% over the same period last year; The newly installed PV capacity in China is 113.16GW (113 million KW). For the first time, the annual installed capacity of photovoltaic
in China has exceeded 100 million kilowatts. In addition, there were 907 hours of solar power generation from January to August, 40 hours less than same period last year; the completed investment in solar power generation projects was 187.3 billion yuan, an increase of 82.7% over the same period last year. On September 18,
according to TrendForce. The increase in production capacity and shipments shows that large-size high-performance modules are rapidly driving the development of the entire industrial chain. In addition, the output power of the N-type 210 mm module has exceeded 700 watts, highlighting the openness and innovation of the 210 mm product technology platform.
3. Set another world record! The full-area conversion efficiency of the HBC module reaches 24.88%!
On September 19, the HBC (Hybrid Back Contact Heterogeneous Battery) module, developed by Fujian Jinshi Energy Co., Ltd. and the National Engineering Research Center for High Efficiency Solar Cell Equipment and Technology, was tested and certified by TUV North Germany, a global authority, with a total area conversion efficiency of 24.88%. Set a new world record for the conversion efficiency of full-size crystalline silicon solar cell modules! The module adopts the high-efficiency HBC battery independently developed by Jinshi Energy, which combines scientific and advanced graphical design, low-damage scribing technology, low-temperature interconnection technology and high-density packaging scheme of BC battery.
< Project Progress >
on September 19. The first production line of Shijiazhuang Jingao Solar Energy Technology Co., Ltd., located in Shijiazhuang High-tech Zone, Hebei Province, with a total investment of 10.2 billion yuan, was successfully put into operation.
The project is divided into two phases, and the first production line put into operation belongs to the first phase of the project. The first phase of the project is expected to be completed by the end of October this year, and reach the trial production conditions, and achieve full production by the end of November. After the completion of the first phase of the project, the annual output value will reach 13 billion yuan, the annual tax revenue will be about 350 million yuan, and more than 3000 jobs will be provided. After the completion of the second phase of the project, it will have the production capacity of 10g W crystalline silicon solar slices and 10g W batteries every year.
239.15 billion yuan! On the evening
of September 19, Longji Green Energy announced that the company planned to invest 3.915 billion yuan to build Tongchuan 12 GW high-efficiency monocrystalline battery project, which had been approved by the eleventh meeting of the fifth board of directors in 2023. The estimated total investment and production time of the project disclosed this time have changed from the first disclosure in April. The total investment amount of the project is expected to change from the initial 3.5 billion yuan (including working capital) to 3.915 billion yuan (including working capital); the project was initially planned to reach the production capacity by the end of 2024, and now it is postponed to November 2025.
Recently, the State Energy Group issued a pre-qualification announcement for the public bidding for the procurement of group-level photovoltaic modules in 2023. The total capacity of this centralized procurement is estimated to be 10GWp, including 3GWp for P-type components and 7GWp for N-type components. The specifications are 540Wp and above for monocrystalline single/double-sided P-type components and 565Wp and above for monocrystalline single/double-sided N-type components. The purchase contract is valid until December 31, 2024.