On January 28, the construction sites of key projects in Fengkai County were in full swing. At present, the building materials project of Dapai Mine in Fengkai County is progressing smoothly and orderly.
Fengkai County Dapai Mine Building Materials Project started in May 2021, invested 6.9 billion yuan by Zhaoqing Runxin New Materials Co., Ltd., located in Changgang Town and Luodong Town, leased about 7000 mu of land, mainly producing building stones, prefabricated buildings, building aggregates, machine-made sand, etc., as an important raw material for the base of Huarun Building Materials Industrial Park.
At present, Fengkai is firmly seizing the strategic opportunity of Shenzhen-Zhaoqing building materials trading cooperation, gathering upstream and downstream industrial chains, accelerating the development of aggregates, new materials, prefabricated buildings and other industries, making every effort to build a green building materials industry base in Dawan District, and transforming resource advantages into development advantages.
At present, the No.1 ore transportation road of the mine infrastructure has been connected to the west mining area; the No.2 ore transportation road has been basically completed; the construction of the No.1 waste dump has been completed by about 85%, and the trial production has been started; the earthwork excavation has been completed by 60% of the total quantities. The site and pile foundation construction of the
processing zone have been completed, the main structure works have been completed by about 99%, and the mechanical and electrical installation works have been completed by about 92%. The total length of the tunnel in Section 8 of
the Belt Corridor is about 2.8km, and the construction of each section is progressing in an orderly manner. The total length of the construction access road is about 8.8 kilometers, and about 5.3 kilometers have been opened to traffic. It is planned to be commissioned with load linkage in June 2023. The pile foundations of three round silos and storage sheds in the
wharf storage area have been completed, the excavation, pile breaking and cushion construction of the three round silos have been completed, and the foundation construction has been started; the excavation and pile breaking of the storage sheds have been started; it is planned that the load linkage test run will be carried out in June 2023.