the third-line construction? Let's watch today. Href = "https://price.ccement.com/pricenewslist-1-350000-0.
▲ 2004 Jianfu Factory Panorama
Fujian Cement Co., Ltd. (Hereinafter referred to as Fujian Cement) is Fujian Energy Group Co., Ltd. The strategic business unit of the Company (hereinafter referred to as Funeng Group) is one of the first five listed companies in Fujian Province, with registered capital. 3.
In 2000, Fujian Cement moved its headquarters from Yongan to Fuzhou Jianfu Building and is now located in Funeng Fangyuan Building. At present, the company is still the largest cement production supplier in Fujian Province.
Yongan Cement Plant is located in the Kengbian section of Caoyuan Town, about 10 kilometers northwest of Yongan City. There are rich high-grade limestone ore and clay ore in the plant area and its vicinity, both of which are the essential raw materials for cement production. Therefore, the cement plant is located here with unique geographical advantages.
At that time, Yongan Cement Plant was listed as a national key construction project. In June 1958, the preparatory work was officially started, and the "Preparatory Office of Fujian Yongan Cement Plant" was established. After careful study, it was decided to build two sets of 4 × 42 millipore kilns with an annual output of 450,000 to 500,000 tons of clinker. In the initial stage of
preparation, the leaders of the Ministry of Construction and Fujian Province attached great importance to it, and Soviet experts from the Cement Industry Design Institute of the Ministry of Construction also participated in the site selection work. In July 1959, the preparatory work was basically completed and the construction conditions were met. On December 15 of the same year, the main plant broke ground and started construction.
Cadres and masses work side by side during the day and have a heart-to-heart talk under the kerosene lamp at night to discuss the construction plan and look forward to a better future. During the three-year difficult period, while completing the limestone production task and doing a good job in the maintenance of infrastructure projects, a large number of laborers were transferred to support agricultural production, and they began to open up wasteland and grow melons and vegetables by themselves.
1971, a series of single machine test runs were started. The first ignition of the kiln was at 0:10 on February 24, and the eighth ignition was successful at 4:51 on March 20. However, due to the failure of the feeding system at the kiln tail, the kiln operated intermittently for an hour.
After more than 20 days of renovation, five consecutive ignitions were carried out from April 25 to 27, all of which resulted in confusion in command due to lack of experience, unskilled operation and frequent equipment accidents, and could not operate continuously.
From the first ignition of Dayao on February 24 to the beginning of simple production, to July 7, a total of 22 times of ignition, lasted more than four months, producing 1282 tons of cement.
the plant completed the first set of kiln technology in March 1972 and formally put into operation in April of the same year. Then the second set of kiln was constructed, which was basically completed in October 1974, formally put into operation in January 1975, and the third set of cement mill was installed and delivered to production in June.
So far, Yongan Cement Plant has basically completed two sets of Lipol kiln production process lines, forming an annual production scale of 470000 tons of cement, and has entered the ranks of large and medium-sized cement enterprises in the country.
3 # kiln started trial production in March 1987, running for 3995 hours in that year, with an hourly output of 26.59 tons and a clinker production of 106,000 tons; Production of clinker in 1988 22.
At the end of November 1998, the plant again invested nearly 10 million yuan to carry out the technical transformation of burning anthracite instead of bituminous coal in 3 # kiln. On January 5, 1999, the trial production after the technical transformation of burning anthracite was carried out, and the trial burning of anthracite at the kiln head was successful at one time, setting a precedent for burning anthracite in NSP kiln with all equipment made in China.
In 1990, the cement production and sales volume of Fujian Cement exceeded 1 million tons, making a historic breakthrough. After 30 years of unremitting efforts of two generations, Fujian Cement has finally realized the original idea of "annual output of one million tons of cement".
▲ New dry process cement clinker production line
with a daily output of 4500 tons At present, the company has 7 new dry process clinker cement production lines, with an annual output of 954 clinker.
By the end of December 2022, the company's cement clinker production capacity ranked first in Fujian Province.