the Beginning of Summer, the temperature of the Alkali Project site has been soaring step by step, and the project construction has entered a comprehensive sprint period of commissioning. "Changing the old appearance into a new one", in the project site, you can see the figure of the project builders who are ready to go and run with small steps.. The successful completion of the project nodes and the certainty of the next target node are all injecting continuous confidence into the project to be commissioned on schedule.
On May 13, the first office meeting of the project commissioning headquarters was held in the conference room of the production command center. Dai Jifeng, executive deputy commander-in-chief of the
commissioning headquarters, presided over the meeting. Ding Ximei, commander-in-chief of the commissioning headquarters, Wu Bateer, Yang Jianguo, deputy commander-in-chief of the commissioning headquarters, and the heads of the commissioning expert group, the engineering group, the operation guarantee group, the technical support group and the comprehensive group attended the meeting.
Dai Jifeng pointed out that the project has entered the sprint stage of test run. According to the overall deployment and requirements of Boyuan Group and yuanxing Company, the commissioning organization of Alashan Tamusu Trona Development and Utilization Project is established, which is fully responsible for the unified command, coordination and organization of all departments, participating units and work in the process of project construction, production preparation, single machine commissioning, linkage commissioning and chemical feeding start-up, so as to ensure the commissioning work. Achieve the project construction objectives on schedule. Wu Bartel further clarified the composition and responsibilities of the professional groups of the headquarters, and put forward relevant requirements.
Ding Ximei determined the important time nodes of boiler ignition, steam turbine power generation, mechanical completion of alkali processing plant, water linkage and chemical feeding. The specific work contents of the recent public works, the special water supply project of the Yellow River, the communication and telephone dispatching in the plant area, the technical and commissioning schemes were further decomposed and arranged.
It is reported that the 1 # boiler of the steam and electricity cogeneration plant of the Alkali Project is scheduled to ignite in late May, and the 1 # steam turbine unit will generate electricity in late June; The first production line of the alkali processing plant will be mechanically completed in mid-June and commissioned at the end of June.
Information: Boyuan Group is the major shareholder of yuanxing Energy. Currently, it is not engaged in the production and sales of trona chemical products (soda ash and baking soda), and does not compete with yuanxin Energy.