Investigation Institute: I was "swindled"? I can't get the money after finishing the project.

2023-09-06 15:51:06

A total of 3.6664 million yuan has been paid for the survey, and the overpaid survey fee of 3.1107 million yuan is required to be returned.

The contract does not look carefully: the money did not get in hand, all the hard work in vain?

Recently, the audit report of a survey project has caused a great disturbance. The protagonist of the

story is a survey project in Guangxi, which is currently undergoing a settlement audit.

According to the process, the settlement submitted for review is 12.2215 million yuan. According to the contract and relevant provisions, after preliminary review, the deduction amount is 10.3693 million yuan, and the settlement price after deduction is 1.8522 million yuan. 30% of the engineering survey fee shall be paid within 10 working days after the survey results are submitted

according to the process, and 555,700 yuan shall be paid.

It is reasonable to say that the returned contract payment should only be a small part of it. The audit unit indicated in the announcement letter that it had paid a total of 3.6664 million yuan for the survey and asked for a refund of the overpaid survey fee of 3.1107 million yuan. What kind of trouble is this?

The audit unit gave the following three reasons for returning the amount:

according to the screenshot of the letter, the settlement amount was 12.2215 million yuan, but the audit unit severely deducted 10.3693 million yuan, and the settlement price after deduction was 1.8522 million yuan. Such a large deduction is not equivalent to working for nothing. The reasons given by the audit

unit are as follows:

1. First of all, the audit unit believes that the survey unit has not provided enough on-site photos. Although 263 core photos were provided by the survey unit, 9 photos were missing. And there are no site photos in the construction survey. The survey unit is indeed a big omission in the construction survey.

2. Secondly, the audit unit also grasped a key word. The survey unit said in the contract that it would make full use of the detailed survey drilling, but in fact it did not make full use of this technology in the construction survey, so it deducted the cost of the unused drilling.

This really fully reflects the degree of prudence of the audit unit and the ability to control the details, after all, the survey unit clearly promised the use of detailed survey boreholes, but did not fully fulfill the seized handle can not be defended.

3. Finally, they also mentioned that the construction survey did not start from the excavated foundation trench, but directly from the ground. Because construction from the ground can provide better working surface and construction conditions, but at the same time, it also wastes a lot of drilling costs. Starting from the ground, the working surface and construction conditions are indeed conducive to the survey units, and it will indeed waste a lot of drilling costs. It is not entirely unreasonable for

audit units to deduct fees. How to say, both sides are not fuel-efficient lamps, but the audit unit is too ruthless.

All can be viewed after purchase
Correlation

A total of 3.6664 million yuan has been paid for the survey, and the overpaid survey fee of 3.1107 million yuan is required to be returned.