Six cement enterprises failed to complete the task of peak staggering! The list is published

2023-08-31 16:01:25

On August 30, Chongqing Economic and Credit Commission issued an announcement on the update of cement clinker production lines in Chongqing, which showed that there were 46 clinker production lines in 31 enterprises in Chongqing. From the remarks column of the list, it can be seen that 10 clinker production lines of 6 enterprises have not completed the production task of peak staggering in 2022.

On August 30, Chongqing Economic and Credit Commission issued an announcement on the update of cement clinker production lines in Chongqing, which showed that there were 46 clinker production lines in 31 enterprises in Chongqing. It can be seen

from the remarks column of the list that 10 clinker production lines of 6 enterprises have not completed the production task of peak staggering in 2022, namely:

1 Dongfang Hope Chongqing Cement Co., Ltd.: 5 4800t/d clinker production lines;

2 Chongqing Fuhuang Building Materials Co., Ltd.: one 4960t/d clinker production line;

3 Chongqing Fufeng Cement Group Special Cement Co., Ltd.: one 4500t/d clinker production line;

Huaxin Cement Chongqing Fuling Co., Ltd.: one 4,600t/d clinker production line;

Chongqing Xinjianan Building Materials Co., Ltd.: one 2,500t/d clinker production line;

6 Chongqing Zhengyang New Material Co., Ltd.: one 2500t/d clinker production line.

In addition, Eight 2500t/d clinker production lines of four enterprises, including Chongqing Changshou Southwest Cement Co., Ltd., Chongqing Wanzhou Southwest Cement Co., Ltd., Chongqing Qijiang Southwest Cement Co., Ltd. and Chongqing Jinjiu Building Materials Group Co., Ltd., have been announced to be relocated.

In order to actively respond to the national environmental protection policy and implement the concept of green and low-carbon development, China Cement Network will hold the "2023 Cement'Double Carbon 'Conference and the 10th China Cement Energy Conservation and Environmental Protection Technology Exchange Conference" in Zhengzhou, Henan Province, from September 12 to 13, 2023. The cement industry is moving towards a low-carbon, more energy-saving and greener high-quality development.  

At the same time, the medal ceremony of "2023 Advanced Enterprises of Double Carbon in Cement Industry" and the "Double Carbon" Equipment Exhibition will be held. After the meeting, we will also organize a visit to Jiyuan Zhonglian Cement Co., Ltd. "The world's first production line of carbon sequestration auxiliary cementitious materials and low-carbon cement from flue gas CO2 of steel slag capture cement kiln".

All can be viewed after purchase
Correlation

On August 30, Chongqing Economic and Credit Commission issued an announcement on the update of cement clinker production lines in Chongqing, which showed that there were 46 clinker production lines in 31 enterprises in Chongqing. From the remarks column of the list, it can be seen that 10 clinker production lines of 6 enterprises have not completed the production task of peak staggering in 2022.

2023-08-31 16:01:25