Recently, the photovoltaic power generation projects of Jidong Cement, Huarun Cement and Shangfeng Cement have made new progress. The 2MW photovoltaic project
of Jidong Cement Zanhuang Company was successfully
connected to the grid. "It runs normally and successfully.." At 13:50 p.m.
on December 20, with the successful closing of the photovoltaic grid-connected cabinet, the 2m W photovoltaic power generation project of Jidong Cement Zanhuang Company was successfully connected to the grid, marking a new step on the road of green and low-carbon development.
From project approval to grid-connected power generation, the construction period is only 48 days, which once again refreshes the project speed. The successful grid connection of this project is also the first grid connection project completed by Hebei Development and Reform Commission in 302 ground distributed photovoltaic projects in 2023. After all the distributed photovoltaic power generation projects
of Zanhuang Company are connected to the grid, the average annual power generation can reach 2.45 million kilowatt-hours, which will strongly boost the company's green and clean energy construction and make positive contributions to the early realization of the "double carbon" goal and the promotion of high-quality development.
On December 18,
China Resources Midu Cement Plant held the commencement ceremony of the distributed photovoltaic project.
It is reported that the total investment of the project is about 27 million yuan, the installed capacity is 6.6 MW, and the average annual power generation is about 9.178 million kWh after the completion of the project. It can save about 3520 tons of standard coal, reduce carbon dioxide emissions by about 5854.65 tons, reduce sulfur dioxide emissions by about 26.4 tons, reduce energy costs by about 1 million yuan, and increase tax revenue by about 6 million yuan, which is an important exploration of the integration and development of multi-format industries of China Resources Group, as well as a major practice of green and low-carbon transformation and upgrading of traditional cement industry.
Huarun Hepu Cement 18MWp Distributed Photovoltaic Project Commencement
On December 20, the commencement ceremony of Huarun Hepu Cement Distributed Photovoltaic Project was successfully held.
The construction of Hepu Cement Distributed Photovoltaic Project is a solid step for China Resources Power Guangxi Company to develop a new generation of clean energy industry. The project is planned to invest in the construction of 18 MWp photovoltaic, which is divided into two phases, the first phase is planned to build 13 MWp, and the second phase is planned to build 5 MWp. After the completion of the
project, it is estimated that the annual average power generation will be 19 million kilowatt-hours, which can save 0.54 million tons of standard coal per year, reduce about 4.6 tons of sulfur dioxide, 4.4 tons of nitrogen oxides, 15000 tons of carbon dioxide and 1.1 tons of smoke and dust emissions per year, compared with the thermal power units with the same power generation capacity, with good economic and social benefits. At the same time, it will alleviate environmental pressure and help the region achieve green and low-carbon development.
Tongling Shangfeng Phase II 4MW Photovoltaic Power Generation Project was successfully connected to the grid
. On December 19, the Tongling Shangfeng Phase II 4MW Distributed Photovoltaic Power Generation Project invested and constructed by Shangfeng Sunshine New Energy Company passed the acceptance and was successfully connected to the grid.
The project makes full use of the open space of Tongling Shangfeng Cement Tailings Mine to build a distributed photovoltaic power station, which is reasonably designed according to the site terrain conditions. The construction of the project has overcome the problems of complex geological conditions on site, carefully optimized the design and construction scheme, completed the construction and installation of a complete set of systems including photovoltaic power generation, inverter, step-up, grid-connected, supporting and auxiliary systems in more than two months, and successfully completed grid-connected power generation within the year. After the
project is put into operation, it is estimated that about 4 million kilowatt-hours of clean electricity will be generated annually, about 1242 tons of standard coal will be saved annually, and about 3312 tons of carbon dioxide emissions will be reduced annually. Relevant person in charge of
new energy said that the follow-up company will coordinate the daily operation and maintenance management of the power station, and work with Tongling Shangfeng Phase I 1.6MW floating photovoltaic project to help Tongling Shangfeng green production, low-carbon development and reduce the cost of comprehensive electricity consumption.