Recently, the People's Government of Linxiang City, Yueyang City, Hunan Province, announced the approval of the environmental impact report form for the construction project of 2.8 million tons/year sandstone mine in Shenglong Mining Area. The 72965 of the project is 0.67 million yuan, and the construction unit is Linxiang Leiming Mining Co., Ltd. On December 30,
2022, Anhui Leiming Kehua Co., Ltd. won the mining right for 356 million yuan. The minable resource of the mine is 57.95 million tons, the annual mining of sandstone ore for construction is 2.8 million tons, and the transfer period is 21.5 years (including one-year capital construction period). It is understood that Linxiang Leiming Mining Co., Ltd. is a wholly-owned subsidiary of Anhui Leiming Kehua Co., Ltd.
According to the report, the project is located in Shenglong Group, Yonghe Village, Tandu Town, Linxiang City. It is mainly composed of open pit area, industrial square, waste dump, etc. The mining area of the open pit area is 0.3375 square kilometers, and the design recovery rate is 98%. The top-down bench mining method is adopted, and the mine is not equipped with explosive magazine and refueling area.
The industrial square area is located in the northwest of the 300m safety range of the mine, with a total area of 77436 square meters, consisting of an ore unloading platform, a crushing and screening workshop, a sand making building, a finished product warehouse, an office building, a canteen, a comprehensive warehouse, a machine repair workshop, an electrical room, a fire pool, a pump station and supporting environmental protection facilities. The
dump is located in the valley under the eastern hillside where the No.2 turning point of the mining area is located, with a total area of 24244 square meters, a ditch top elevation of + 98 meters, a ditch bottom elevation of + 78 meters, a design maximum stacking height of 20 meters, a volume of 327000 cubic meters, a retaining dam at the foot of the dump slope, a stone masonry, a height of 4.5 meters, The lower part of 0.5m is buried underground and connected with the bedrock, the top width is 2m, the outer slope ratio is 1: 0.5, and the inner slope ratio is 1:0; the dumping project is transported by truck-the bulldozer is used for dumping. After the truck is unloaded, the bulldozer pushes the stripping left on the working platform to the stage edge. The three areas are connected by newly built and developed roads in the site, with a total road area of 39885 square meters.