Lowest 1.18 yuan/W! Guangdong Hydropower 2023-2024 Photovoltaic Module Collection Bid Opening!

2023-08-02 10:45:33

Publicity of successful candidates

On August 1, Guangdong Hydropower announced the successful candidates for centralized procurement of photovoltaic modules in 2023-2024. There are eight candidates in the two bidding sections of this announcement. Jingao, Dongfang Risheng, Yidao Xinneng, Tongwei, Zhengtai Xinneng and other companies are among the winning bidders.

Among them, Jingao, Dongfang Risheng, Yiyi Xinneng, Tongwei, Zhengtai Xinneng, Longji Leye and Yijing Optoelectronics are planning to win the bid for P-type components at a unit price of 1.18 yuan/W-1.243 yuan/W; Four enterprises , Yidao Xinneng, Jingke Energy, Zhengtai Xinneng and Jingao , intend to win the bid for N-type components, with the lowest price of 1.25 yuan/W-1.29 yuan/W.

It is worth noting that the lowest unit price of the winning bid has reached 1.18 yuan/W.

On July 6, Guangdong Hydropower issued a centralized procurement announcement for photovoltaic modules in 2023-2024, with an estimated total procurement volume of 5G W. All

the components are purchased according to the bidding of double-sided double-glass components, and the single-sided single-glass components are reduced by 0.02 yuan/Wp on the basis of the unit price of single-crystal double-sided high-efficiency components. Bids that do not respond to this clause will be rejected.

Publicity end time: August 4

, 2023
All can be viewed after purchase
Correlation

On October 27, the Office of Industry and Information Technology of Inner Mongolia issued the Announcement on the Demolition and Withdrawal of the 3 # Clinker Production Line with a Daily Output of 2500 Tons of Ulanchabu Zhonglian Cement Co., Ltd. The 3 # clinker production line of Wulanchabu Zhonglian Cement Co., Ltd. has dismantled the core process facilities such as the cone of the decomposition furnace, the tertiary air duct, the high temperature fan, the tail coal scale and the tail coal conveying system equipment, and the waste heat boiler pipeline at the kiln head, and has fulfilled the procedures for the change of the production permit and the pollutant discharge permit, so it no longer has the conditions to resume the production of cement clinker.