Credit quality project. According
to Liangjiang New Area, in the first half of the year, major projects at the municipal level in Liangjiang New Area completed a total investment of 10.593 billion yuan, with an investment progress of 65.92% and an over-schedule progress of 15.92 percentage points.
Over the past few days, workers have been fighting on the front line to push forward the progress of the project.
At the site of Xinzhi New Energy Vehicle Drive Motor R & D and Production Base, more than 300 workers are busy at various points, and the main steel structure of a three-storey production workshop has been erected, which is expected to be completed in August.
"Subsequently, equipment foundation construction and equipment installation and commissioning will be carried out." Hu Jianxin, the project leader, said that after the completion of Xinzhi New Energy Vehicle Drive Motor, it will have the ability to produce 3 million sets of new energy vehicle motor stator and rotor assemblies annually, which will greatly enhance the development of the new energy vehicle core parts industry in the new area.
As an important carrier of scientific and technological innovation, the incubation accelerator project located in Liangjiang Cooperative Innovation Zone is one of the 248 landmark major projects issued by the Chengdu-Chongqing Shuangcheng Economic Circle Construction Joint Office.
At the EPC project site of the first bid section of the Incubation Accelerator contracted by the Southwest Company of the Seventh Bureau of China Construction, the project is undergoing comprehensive construction of steel structure. At present, 50% of the main project has been completed, and it is expected that all the main construction will be completed by the end of August this year.
The project takes industrial incubation as its core function, aiming at creating a high-quality industrial ecosphere with science and technology innovation platform as the city's cultivation and incubation of scientific research achievements of universities and colleges in the park, incubation space as the engine, supporting high-quality commerce, ecological office space and lakeside talent apartments. The first phase
of Ganfeng New Lithium Battery Science and Technology Industrial Park Project is expected to be completed in September, and the PACK production line is expected to be put into operation by the end of August.
It is understood that the project officially started construction on July 30 last year, with a fixed investment of more than 5 billion yuan, and will build the largest solid-state battery production base in China, including three sub-projects of solid-state battery technology research Institute, solid-state battery production base and battery Pack system. After the project is put into operation, it will help Chongqing build a trillion-level intelligent network new energy automobile industry cluster, improve the new energy automobile industry chain in the new area, and promote the industry to the middle and high end of the value chain. The investment
of Huaneng Liangjiang Gas Turbine Phase II Project will reach 4.2 billion yuan, and the concrete construction of the main plant is under way. It is planned to build a 3 × 700 MW (H-class) gas-steam combined cycle unit, with an annual power generation of about 8.4 billion kWh after completion and commissioning. After the completion of the second phase
of Huaneng Liangjiang Gas Turbine Project, the total installed capacity of Huaneng Liangjiang Gas Turbine will reach 3 million kilowatts, and the annual power generation capacity will reach more than 10 billion kilowatt-hours, which will significantly enhance the "bottom-up" power supply capacity in Chongqing and greatly enhance the level of power security in Chongqing.
In addition, a number of major projects at the municipal level, such as the plant of Dadi (International) Life Science Park, the East Section of Yulin River on Liuheng Expressway, the Citizen Center of Liangjiang New Area and the expansion project of the People's Hospital of Liangjiang New Area, are accelerating synchronously.