Recently, according to the survey of digital building materials, the continuous high temperature in Suzhou area of Jiangsu Province has affected the construction conditions. At present, the progress of a large number of local infrastructure construction projects has slowed down, affecting the shipment of concrete mixing stations.
It is understood that due to the impact of high temperature, the construction progress of local projects is slow, and the shipment volume of mixing stations has been greatly reduced. According to the feedback from local concrete enterprises in Suzhou, compared with the same period in previous years, the shipment volume has dropped by at least 25% -30%, and now the average monthly shipment volume is only about 60000 square meters.
Another concrete mixing station said that the current concrete shipment volume has dropped by about 30% compared with the same period in previous years, and the ex-factory price of concrete has also dropped by about 20% compared with the same period in previous years.
In addition, due to the difficulty of landing funds for large-scale local infrastructure projects, infrastructure projects have also been significantly reduced compared with previous years, the above-mentioned enterprises said that the main supply projects are only real estate projects.
浙公网安备33010802003254号