on October 13, the Vietnam Dayang 6600t/d clinker cement production line project contracted by Sinoma International (Nanjing) and constructed by Suzhou Sinoma was successfully ignited and put into operation.

The project commenced on March 24, 2021. Affected by the COVID-19 epidemic, the domestic kiln preheater manufacturing and installation construction personnel could not be present, the equipment and materials were detained at the port and shipped slowly, and the Vietnamese local employees were blocked from returning to work after the Spring Festival, which added difficulties to the project construction. With the full cooperation of all departments of the company, all the staff of the project United as one to overcome difficulties and strictly implement the company's management regulations. On the premise of ensuring epidemic prevention and control and safe production, they vigorously promoted localized construction, carefully organized and steadily promoted the progress of the project, and achieved the smooth performance of the project, which fully demonstrated the spirit of Suzhou Sinoma. It has won high praise from the owners.

The project department will continue to organize meticulously and do a good job in the follow-up work, so as to reach the production standard and obtain the PAC certificate as soon as possible. Xu Yaping, Deputy General Manager of

Suzhou Sinoma, Zhang Yinhu, Assistant General Manager and General Manager of Vietnam Subsidiary, and the project site management team jointly attended the ignition ceremony.
浙公网安备33010802003254号