the Lunar New Year, just after the Beginning of Spring, news came from the ACC TIKARIA grinding station project of Tianjin Cement Institute in India. At 8:00 p.m. local time on February 5, 2022, under the joint witness of the owner, LNVT and the subcontracting team, the TIKARIA grinding station project was successfully fed at one time, and the first batch of cement was produced, completing the task 6 days ahead of the contract requirements. On the afternoon of February 8, the first bag of cement was produced smoothly. In order to commend the efforts and contributions made by the project team of Tianjin Cement Institute to the TIKARIA Grinding Station Project, the owner ACC specially presented a trophy to the project team to express his gratitude.
The TIKARIA grinding station project contract was formally signed on December 20, 2019, during which the project was suspended for one year due to the Indian epidemic. In January 2021, the project was officially restarted. Despite the impact of the epidemic and India's visa policy, the project team of Tianjin Cement Institute could not reach the site, but the project team actively innovated the management mode, made full use of LNVT's local resources in India, and set up a joint project department to implement the project. With careful planning, precise organization and innovative management, the project team of Tianjin Cement Institute and the LNVT project team successfully coped with a series of unfavorable factors such as the second round of epidemic outbreak in India and the soaring shipping prices, thus ensuring the normal progress of the project. The Joint Project Department has formulated detailed standardized process documents (SOP) for the key elements of project implementation, established a regular video weekly meeting system among the project management team, design team, procurement team and LNVT team of Tianjin Cement Institute, and coordinated all parties to solve problems quickly through online dynamic problem tracking list; The establishment of high-quality subcontractor resource library can achieve the allocation of superior resources at any time; make full use of the BIM platform of Tianjin Cement Institute, combine with three-dimensional model and animation to solve the installation and commissioning problems encountered on site online in time, and arrange a number of online training and online installation and commissioning guidance, which has achieved good results.
TIKARIA Grinding Station Project is another successful cooperation between Tianjin Cement Institute and ACC Lahau of India after SINDRI Grinding Station Project. Both projects adopt the EPC general contracting mode with low recognition in the Indian engineering market, and it is also the first time for ACC Lahau of India to try the overall project EPC contracting mode in India. SINDRI grinding station project has completed the cement node on January 2, 2021, 9 days ahead of the contract period. At present, the first cement contract node of TIKARIA grinding station project has been realized ahead of schedule again, which has once again demonstrated the strong general contracting performance and anti-risk ability of Tianjin Cement Institute to India Lahao ACC, laid a solid foundation for the subsequent development of the Indian general contracting market, and won a good reputation for SINOMA brand in the Indian market.
The Joint Project Department will continue to explore and innovate the collaborative management mode, coordinate the upstream and downstream industrial chains, successfully complete the follow-up tasks of the project, continue to advance for the implementation of the internationalization strategy of Sinoma International, and strive for the construction of a world-class enterprise with global competitiveness for China Building Material Group.