Announcement of Replacement Plan for a New 4500t/d Clinker Production Line

2021-03-06 12:52:21

Chifeng Shanshui yuanhang Cement Co., Ltd. intends to integrate the existing one dry kiln cement production line with a daily output of 2500 tons and one dry kiln cement production line with a daily output of 2000 tons, and build a cement clinker production line with a daily output of 4500 tons in Lime Kiln Village, Shijia Manchu Township, Haraqin Banner.

On March 5, the Inner Mongolia Office of Industry and Information Technology issued a public announcement on the capacity replacement plan for the relocation project of the 4500-ton cement clinker production line of Chifeng Shanshui yuanhang Cement Co., Ltd. Chifeng Shanshui yuanhang Cement Co., Ltd. intends to integrate the existing one dry kiln cement production line with a daily output of 2500 tons and one dry kiln cement production line with a daily output of 2000 tons, and build a cement clinker production line with a daily output of 4500 tons in Lime Kiln Village, Shijia Manchu Township, Haraqin Banner.

The project is scheduled to be put into operation in July 2023.

The announcement is as follows:

In accordance with the spirit of the Guiding Opinions of the State Council on Resolving the Serious Contradiction of Overcapacity (Guo Fa [2013] No.41), In accordance with the requirements of the Notice of the Ministry of Industry and Information Technology on the Issuance of Measures for the Implementation of Capacity Replacement in the Iron and Steel Cement Glass Industry (No.337 of the Ministry of Industry and Information Technology) and the Notice on Serious Capacity Replacement and Strict Prohibition of New Capacity in the Cement Flat Glass Industry (No.57 of the Ministry of Industry and Information Technology), the Ministry of Industry and Information Technology issued the Notice. Chifeng Shanshui yuanhang Cement Co., Ltd. intends to integrate the existing one dry kiln cement production line with a daily output of 2500 tons and one dry kiln cement production line with a daily output of 2000 tons, and build a cement clinker production line with a daily output of 4500 tons in Lime Kiln Village, Shijia Manchu Township, Haraqin Banner. The capacity replacement plan for the relocation project of the cement clinker production line with a daily output of 4500 tons of Chifeng Shanshui yuanhang Cement Co., Ltd. is now publicized for the period from March 5 to March 11, 2021. If there is any objection, please give feedback to our office within the publicity period.

Tel: 0471-4826452 (fax)

Attachment: Capacity Replacement Plan

for the Relocation Project of the 4500t/d Cement Clinker Production Line of Chifeng Shanshui yuanhang Cement Co., Ltd. On March 5

, it was reported that on February 25, the Inner Mongolia Development and Reform Commission issued a number of safeguards to ensure the completion of the "14th Five-Year Plan" energy consumption double-control target task (draft for comments) . From 2021 , Coke (semi-coke), calcium carbide, polyvinyl chloride (PVC), synthetic ammonia (urea), methanol, ethylene glycol, caustic soda, soda ash, ammonium phosphate, yellow phosphorus, cement (clinker) , flat glass, graphite electrodes below ultra-high power, iron and steel (which have entered the stage of capacity replacement publicity) will no longer be examined and approved. According to the national regulations), ferroalloy, electrolytic aluminum, alumina (except alumina extracted from high-alumina fly ash), sapphire, polycrystalline silicon without downstream conversion, monocrystalline silicon and other new capacity projects, if it is really necessary to construct, must implement capacity and energy consumption reduction replacement in the region.

All can be viewed after purchase
Correlation

Chifeng Shanshui yuanhang Cement Co., Ltd. intends to integrate the existing one dry kiln cement production line with a daily output of 2500 tons and one dry kiln cement production line with a daily output of 2000 tons, and build a cement clinker production line with a daily output of 4500 tons in Lime Kiln Village, Shijia Manchu Township, Haraqin Banner.

2021-03-06 12:52:21

From September 22, 2025 to September 28, 2025, the highest opening rate of cement kilns in all provinces in China is Tianjin, with the opening rate of 100.00%. Kiln opening rate of 50% and above: 66.72% in Anhui Province, 61.98% in Shandong Province, 59.02% in Henan Province, 56.68% in Jiangsu Province, 50.00% in Liaoning Province and 50.00% in Hainan Province.