Flow mark! Reject the bid! Postponement! Nearly 1GW photovoltaic projects have changed!

2026-01-19 19:17:05

On January 16, the EPC general contractor of Yangquan Distributed Photovoltaic Project in Wulan Town, Etuoke Banner, Inner Mongolia issued a bid announcement, which was due to the fact that less than three bidders submitted bidding documents at the bid opening stage.

On

16 January, Sheep pen, Wulan Town, Etuoke Banner, Inner Mongolia " has been deferred 4 times." The deadline for submission of project bidding documents and the time for bid opening have been extended from 9:30 a.m. on October 22, 2025 to 9: 30 a.m. on January 16, 2026.

" This project is divided into 1 bid section . The content of the bid section is the EPC general contracting of the new 100MW Yangquan Photovoltaic Power Generation Project, including the design, construction, acceptance, handover and other general contracting contents of the project.

In addition to the above projects, there are also a number of projects in the near future, such as flow mark, delay and other abnormal situations.

On January 19, Ganzhou Xingzhiyuan Project Management Co., Ltd. The reason is that the substantive response of the project is less than quorum .

On January 19, Guoneng Ningxiang DC supporting Hongsibao 1.5 million kilowatt new energy base project general contracting (the first tender section)-the second photovoltaic area foundation project tender section project announcement said that. The deadline for submission of response documents for this bid section is changed to 16:00 p.m. on January 23, 2026.

On January 16, Erbil Erbi1125 MWp Photovoltaic Power EPC General Contracting Project issued another extension announcement. It is worth noting that the project has been postponed six times, and the bid closing/opening time has been postponed from 9:00 on September 19, 2025 to 9:00 on January 29, 2026.

On January 16 , CGN Jianhu County, Jiangsu Province Fishing-photovoltaic Complementary Phase II 200 MW Photovoltaic Power Generation Project EPC General Contracting Project issued postpone the bid closing/opening time of the bidding documents. The specific time is to be determined and will be notified 3 working days in advance.

Previously, the closing/opening time of bidding documents for the project was postponed from 9:30 on January 15, 2026 to 9:30 on January 22, 2026.

On January 16 , the roof distributed photovoltaic project of Heyuan Branch Center of Lingnan Modern Agricultural Science and Technology Laboratory in Guangdong Province issued a notice of bid rejection because the number of valid bidders was insufficient. Procurement failed .

On January 14 , the EPC general contracting bidding of roof distributed photovoltaic power generation project (Phase I) of Shanxi Xiangyang Mining Group Co., Ltd. was postponed, and the submission/opening time of bidding documents was postponed to 14:30 on January 30, 2026.

It is understood that the total installed capacity of the project is 12. 02811 MWp (AC side capacity) 10.

On January 13 , the roof distributed photovoltaic power generation project of Licheng Kechuang Center issued a (second) announcement of bid rejection. After the review of the

Bid Evaluation Committee, it is unanimously agreed that the suppliers Fujian Yefeng Electric Power Construction Engineering Co., Ltd., Shenzhen Skyworth Photovoltaic Technology Co., Ltd., Yete Construction Co., Ltd. and Xiamen Branch of Zhengneng (Fujian) Construction Engineering Co., Ltd. fail to substantially respond to the requirements of the bidding documents, and the technical compliance review is not passed, which will be regarded as invalid bidding. As there are less than 3 valid bidders, the bid of this project is rejected according to law. On the day of bid

rejection, the project immediately issued the third tender announcement of the project. The project is located in Licheng District, Quanzhou City, Fujian Province, and the tenderer is Quanzhou Lijian New Energy Technology Co., Ltd.

On January 12 , the first batch of industrial and commercial 100MW distributed photovoltaic (EPC) projects in Yunnan area of Yunnan Mekong New Energy Development Co., Ltd . The reason for the failure of bidding is that the bidding documents submitted by the bidders have not been received by 14:00 on January 9, 2026, and the tenderee will re-invite tenders according to law.

It is reported that the total investment of the project is 200 million yuan, and the purchaser is Yunnan Mekong New Energy Development Co., Ltd.On December 26 ,

2025, Lingyuan Sihedang 300MWp Centralized Parity Photovoltaic (EPC) Project issued a notice of bid rejection. The announcement shows that the reason for the rejection of the project is that the number of valid bidders is less than statutory three .

Previously, according to Digital New Energy DataBM, the reason for the change of the project was either a major change in the project or less than three response units.

All can be viewed after purchase
Correlation

The People's Court of Hanshan County, Maanshan City, Anhui Province, is scheduled to conduct a public auction of 41 sets of machinery and equipment involved in the case of Maanshan Jingsheng Energy Technology Co., Ltd. from 10:00 on May 11 to 10:00 on May 12, 2026 (except for delays), with a starting price of 2.08075 million yuan and a price increase of 1000 yuan. The deposit is 120000 yuan.

2026-04-27 11:00:13

Digital New Energy DataBM. Com learned that on April 16, the Development and Reform Commission of Cele County, Xinjiang, issued a solemn statement.

2026-04-27 09:09:12

This opinion emphasizes the principle of giving priority to conservation, coordinating development and security, systematically promoting energy conservation and carbon reduction through industrial optimization, energy transformation, energy conservation in key areas, strict supervision and policy and technical support, and supporting carbon peak, carbon neutralization and green and high-quality development.

2026-04-24 10:28:26

The battery can be charged to 80% of the theoretical capacity in only 10 minutes under high-rate charging conditions, and can still operate stably after thousands of charge-discharge cycles, showing excellent durability of fast charge cycles.

2026-04-23 10:48:10

What is happening in the cement industry?

2026-04-23 07:02:02

On the morning of April 21, 2026, the Information Office of the State Council held a press conference to introduce the development of industry and information technology in the first quarter of 2026. Zhang Yunming, Vice Minister of the Ministry of Industry and Information Technology, attended the press conference, together with Tao Qing, spokesman of the Ministry of Industry and Information Technology and Director of the Bureau of Operation Monitoring and Coordination, and Xie Cun, spokesman of the Ministry of Industry and Information Technology and Director of the Department of Information and Communication Development, to introduce the situation and answer questions from the press.

2026-04-22 09:23:01

Overall, in March, the scale of raw coal production in industries above the scale (hereinafter referred to as regulated industries) was stable, crude oil production maintained growth, natural gas production accelerated, and electricity production grew steadily.

2026-04-16 10:23:20

On April 16, the National Bureau of Statistics released industrial data above the scale in March 2026.

2026-04-16 10:21:51

Component market price reduction is difficult to promote orders, reverse price increase and decline.

2026-04-15 17:33:20

What is happening in the cement industry?

2026-04-13 07:02:03

The scope of component price reduction continues to expand, and demand at home and abroad weakens.

2026-04-10 18:05:39

The meeting calls for consolidating and deepening the effectiveness of the work of standardizing the order of industrial competition, giving full play to the role of the collaborative working mechanism of departments, continuously and thoroughly promoting the early warning and regulation of production capacity, standardizing price competition, compressing the account period of suppliers, strengthening product quality supervision, cracking down on intellectual property infringement, and governing "involution and externalization".

2026-04-10 09:51:41

On April 3, State Grid E-commerce Technology Co., Ltd., a subsidiary of State Grid, planned to transfer 100% equity and related creditor's rights of State Grid Zhilian (Jilin) New Energy Co., Ltd. in the form of online bidding at a low price of 18 million yuan.

2026-04-08 16:19:52

The People's Court of Jianshui County, Honghe Hani and Yi Autonomous Prefecture, Yunnan Province, will be held from 10: Publicly dispose of part of the renewable energy subsidies receivable from the second phase of Haiwei Photovoltaic Power Station under Jianshui County Ottersview Photovoltaic Power Generation Co., Ltd. (Hereinafter referred to as "Ottersview") on Taobao Ali Auction Platform (from February 7, 2022 to February 28, 2023).

2026-04-07 09:06:41

On March 27, the Bureau of Ecology and Environment of Wenshan Prefecture, Yunnan Province, decided to approve the environmental impact report form of Ganlongtang Photovoltaic Power Generation Project.

2026-04-07 09:04:12

Domestic concrete price statistics in March showed that the statistics covered many parts of the country. From the overall data, the national concrete price has a slight change, with a ring-to-ring change of 0.02% and a year-on-year change of-10.42%. Prices in some areas remained unchanged during the statistical cycle, with a month-on-month change of 0.00% in Beijing, Tianjin and other places. The change is more obvious in Liaoning, with a ring ratio of 0.37%, while Hainan is only-1.33% year-on-year, and the change is relatively moderate. The range of price changes in different regions shows certain differences.

2026-04-01 11:08:02

What is happening in the cement industry?

2026-03-29 07:02:03

Lianyungang Pumped-storage Power Station is a first-class large (1) project. Its pivotal structures are mainly composed of upper reservoir, lower reservoir, water conveyance system, underground powerhouse system and ground switching station. The installed capacity of the power station is 1200 MW, which is a daily regulation power station. The power station is equipped with four single-stage vertical shaft mixed-flow reversible pump-turbine generator units with a single unit capacity of 300 MW and a rated head of 425m.