16 January, Sheep pen, Wulan Town, Etuoke Banner, Inner Mongolia " has been deferred 4 times." The deadline for submission of project bidding documents and the time for bid opening have been extended from 9:30 a.m. on October 22, 2025 to 9: 30 a.m. on January 16, 2026.
" This project is divided into 1 bid section . The content of the bid section is the EPC general contracting of the new 100MW Yangquan Photovoltaic Power Generation Project, including the design, construction, acceptance, handover and other general contracting contents of the project.
In addition to the above projects, there are also a number of projects in the near future, such as flow mark, delay and other abnormal situations.
On January 19, Ganzhou Xingzhiyuan Project Management Co., Ltd. The reason is that the substantive response of the project is less than quorum .
On January 19, Guoneng Ningxiang DC supporting Hongsibao 1.5 million kilowatt new energy base project general contracting (the first tender section)-the second photovoltaic area foundation project tender section project announcement said that. The deadline for submission of response documents for this bid section is changed to 16:00 p.m. on January 23, 2026.
On January 16, Erbil Erbi1125 MWp Photovoltaic Power EPC General Contracting Project issued another extension announcement. It is worth noting that the project has been postponed six times, and the bid closing/opening time has been postponed from 9:00 on September 19, 2025 to 9:00 on January 29, 2026.

On January 16 , CGN Jianhu County, Jiangsu Province Fishing-photovoltaic Complementary Phase II 200 MW Photovoltaic Power Generation Project EPC General Contracting Project issued postpone the bid closing/opening time of the bidding documents. The specific time is to be determined and will be notified 3 working days in advance.
Previously, the closing/opening time of bidding documents for the project was postponed from 9:30 on January 15, 2026 to 9:30 on January 22, 2026.
On January 16 , the roof distributed photovoltaic project of Heyuan Branch Center of Lingnan Modern Agricultural Science and Technology Laboratory in Guangdong Province issued a notice of bid rejection because the number of valid bidders was insufficient. Procurement failed .
On January 14 , the EPC general contracting bidding of roof distributed photovoltaic power generation project (Phase I) of Shanxi Xiangyang Mining Group Co., Ltd. was postponed, and the submission/opening time of bidding documents was postponed to 14:30 on January 30, 2026.
It is understood that the total installed capacity of the project is 12. 02811 MWp (AC side capacity) 10.
On January 13 , the roof distributed photovoltaic power generation project of Licheng Kechuang Center issued a (second) announcement of bid rejection. After the review of the
Bid Evaluation Committee, it is unanimously agreed that the suppliers Fujian Yefeng Electric Power Construction Engineering Co., Ltd., Shenzhen Skyworth Photovoltaic Technology Co., Ltd., Yete Construction Co., Ltd. and Xiamen Branch of Zhengneng (Fujian) Construction Engineering Co., Ltd. fail to substantially respond to the requirements of the bidding documents, and the technical compliance review is not passed, which will be regarded as invalid bidding. As there are less than 3 valid bidders, the bid of this project is rejected according to law. On the day of bid
rejection, the project immediately issued the third tender announcement of the project. The project is located in Licheng District, Quanzhou City, Fujian Province, and the tenderer is Quanzhou Lijian New Energy Technology Co., Ltd.
On January 12 , the first batch of industrial and commercial 100MW distributed photovoltaic (EPC) projects in Yunnan area of Yunnan Mekong New Energy Development Co., Ltd . The reason for the failure of bidding is that the bidding documents submitted by the bidders have not been received by 14:00 on January 9, 2026, and the tenderee will re-invite tenders according to law.
It is reported that the total investment of the project is 200 million yuan, and the purchaser is Yunnan Mekong New Energy Development Co., Ltd.On December 26 ,
2025, Lingyuan Sihedang 300MWp Centralized Parity Photovoltaic (EPC) Project issued a notice of bid rejection. The announcement shows that the reason for the rejection of the project is that the number of valid bidders is less than statutory three .
Previously, according to Digital New Energy DataBM, the reason for the change of the project was either a major change in the project or less than three response units.