The New Energy DataBM. Com was informed that on June 13, Guangdong Shaoneng Zhongguan Energy Co., Ltd. issued 300MW distributed photovoltaic and 300Mwh ". The tenderer of the project is Guangdong Shaoneng Zhongguan Energy Co., Ltd . According to the data, the company is a state-owned enterprise , which is 84% owned by Zhongguan Electric Power (Shenzhen) Co., Ltd. and 16% owned by Shaoneng Co., Ltd.
It is understood that the construction site of the bidding project is located in Henan, Hebei and other provinces , with a total planned construction period of 12 months . The winning bidder will sign a framework agreement after winning the bid and carry out the development by stages.
According to the announcement, the bidding project is divided into one bid section . The bidding scope includes but is not limited to:
that consortium bidding 0 HTML0UNK is not accepted for this project 21。 0 HTML0 UNK2 2 Bid closing/opening time is 0 HTML0 UNK2 3 02 26 Jun 25 09:00 0 HTML0 UNK2 4.