People who brave a dangerous situation  in the cold winter! Is the 52.6 Billion Bet on 33 Photovoltaic Projects in 5 Provinces a Big Bet or a Foresight?

2025-06-04 12:21:15

The photovoltaic industry, which once took advantage of the "double carbon" Dongfeng to rise, is now in deep winter, and the serious mismatch of production capacity has led to price collapse, enterprise losses, bankruptcy, layoffs and other phenomena. However, under such a difficult background, the deep-seated chill of the market has not stopped the enthusiasm of some local governments to attract investment for photovoltaic projects. Up to now, many parts of the country are still carrying out investment plans to continue to promote the landing of photovoltaic manufacturing projects.

The photovoltaic industry,

which once took advantage of the "double carbon" Dongfeng to rise, is now in deep winter, and the serious mismatch of production capacity has led to price collapse, enterprise losses, bankruptcy, layoffs and other phenomena.

However, under such a difficult background, the deep-seated chill of the market has not stopped the enthusiasm of some local governments to attract investment for photovoltaic projects. Up to now, many parts of the country are still carrying out investment plans to continue to promote the landing of photovoltaic manufacturing projects. According to Digital New Energy DataBM,

the details of "crazy overweight" photovoltaic projects

in

5 places are as follows:

Karamay City in Xinjiang and Habahe County in Altay have released nine photovoltaic investment projects, with a total investment of over 30 billion yuan , involving crystalline silicon and perovskite batteries, components and other links.

Among them, the investment attraction photovoltaic base project released by Karamay City on January 10 includes 12 GW TOPCon high-efficiency photovoltaic cells and 5G W high-power photovoltaic module production line. Total investment up to 109.

are respectively the new project with annual output of 5G W high-efficiency solar cells, High-efficiency photovoltaic module production project, annual production of 3GW high-efficiency photovoltaic module manufacturing project, inverter and electrical equipment production project.

covers the main industrial chain links of drawing rods, slices, batteries, and modules." As well as silver paste, brackets, spare parts and other supporting projects.

400 million yuan , and the annual production capacity of 2G W photovoltaic modules will be formed after the completion of the project.

For example, on May 21, 2025, the Management Committee of Baotou Equipment Manufacturing Industrial Park in Inner Mongolia issued a public consultation announcement on the Industrial Development Plan of Baotou Equipment Manufacturing Industrial Park (2024-2035). According to

the document, for the solar energy industry, by the end of 2030, the park will add 120GW monocrystalline silicon, 60GW slices, 30GW cells and 30GW modules; By the end of 2035, 50GW of monocrystalline silicon, 25GW of slices, 20GW of cells and 20GW of modules will be added.

are predictable, Promoting the expansion of the local photovoltaic industry is still the https://www.databm. in the next 10 years . same problem exists in the Xi'an municipal government.

On May 15, Xi'an , Shaanxi Province, also issued the Implementation Plan for Xi'an to Support the Capacity Improvement of the Photovoltaic Industry Chain (2025-2027). The production capacity of silicon wafers and batteries in the city reached 120 GW and 130 GW respectively, ranking first in the world in terms of silicon wafer shipments; the production capacity of modules reached more than 10 GW, and the production capacity of inverters exceeded 76 GW .

According to public data, the market share of photovoltaic modules in Shaanxi Province has ranked first in the world for three consecutive years, and the shipment of silicon wafers has ranked first in the world for nine consecutive years.

In addition, in addition to the two areas mentioned above, in January and April 2025, Sichuan Province has issued two documents, namely, Several Measures to Support the Sustainable and Healthy Development of Photovoltaic Manufacturing Industry and Work Program for Building a Strong Chain of New Energy Industry Chain in Sichuan Province (2025-2027).

In terms of the layout of the photovoltaic industry chain, it is required to focus on solving the shortage of production capacity of electronic grade polysilicon, photovoltaic glass, silver paste, crucible, battery components and other links . We will consolidate the scale advantages of polysilicon and high-efficiency solar cells, moderately expand the scale of low-consumption and high-efficiency production capacity such as rod drawing and slicing, and develop cutting-edge products such as new high-efficiency solar cells. At the same time, it is required to speed up the research and development of advanced photovoltaic technologies such as large-size ultra-thin silicon wafers, perovskite batteries and compound thin film batteries.

The document points out that by 2027, an industrial cluster with coordinated development of the whole industry chain will be built, with the output value of the industry exceeding 500 billion yuan, and a photovoltaic industry base with important influence in the world will be built.

In recent years, local governments have long been experienced in attracting investment and promoting the healthy development of local economy. It is impossible not to know the problems faced by the photovoltaic industry, but they still ignore the fact that "overcapacity is serious" and it is urgent to speed up the liquidation. They continue to have great enthusiasm for promoting scale expansion. Is it gambling or foresight? The sobering agent of

people who brave a dangerous situation : "cutting down projects" and "changing the track"

However, while large-scale expansion plans emerge one after another, some local governments and some regions are keenly aware of the industry crisis, thus opening up new ways to wake up from the goal of purely pursuing scale leadership. Anhui Province is a typical representative of the transformation to the leading direction of industrial technology.

On April 10, the Information Office of the People's Government of Anhui Province held the "Year of Concentrating on Building Advanced Photovoltaic and New https://www.databm.2024

with International Influence". Anhui Province promptly persuaded and suspended 7 cross-border cell and module projects, involving more than 80 GW of production capacity; no silicon material and silicon wafer (crystal pulling) projects were introduced throughout the year, and the total production capacity of new contracted photovoltaic cell and module projects decreased by 90% and 82% year on year.

Standing in the mid-term stage of "double carbon", photovoltaic industry, as an important force to achieve carbon emission reduction goals, although many regions actively launch attraction plans according to their own development needs, must not "attract investment for investment" and blindly incre ase investment in photovoltaic industry.

At present, under the pressure of serious mismatch between supply and demand and serious price competition, the main industry chain enterprises of photovoltaic industry have entered a large area of continuous loss.

In this context, local governments should focus more on the application of new technologies, increase investment in R & D, encourage enterprises to carry out technological innovation, improve the conversion efficiency and quality of photovoltaic products, and reduce production costs, rather than just focus on those construction projects that have been "rolled up".

All can be viewed after purchase
Correlation

Digital New Energy DataBM. Com was informed that on September 11, Jiangsu Yongquan Photovoltaic Technology Co., Ltd. was filed for bankruptcy, the court was the Intermediate People's Court of Zhenjiang City, Jiangsu Province, the applicant was Rongma Science and Technology Group Co., Ltd., and the case number was (2025) Su 11.

2025-09-12 15:46:09

Digital New Energy DataBM. Com learned that on September 8, four photovoltaic power generation project owners, such as Nongxian, Ruili City, Dehong Prefecture, Yunnan Province, issued a competitive consultation announcement with a total scale of 171 MW.

2025-09-11 17:45:31

On September 8, the Beijing Property Exchange disclosed that the 9% equity of Dezhou Jusheng New Energy Technology Co., Ltd. (Hereinafter referred to as "Jusheng New Energy") was listed at the transfer base price of 1 yuan, and the transferor was Jiangxi Electric Power Construction Co., Ltd. of China Electric Power Construction Group (hereinafter referred to as "Jiangxi Electric Power Construction").

2025-09-11 16:44:10

The 20-year right to use distributed photovoltaic construction resources on the roofs of 101state-owned assets in Ezhou, Hubei is being transferred

2025-09-11 16:44:03

On September 5, the procurement project of Pingchuan Substation 500000 kW/2 million kWh New Energy Storage Special Action Project (Phase I) in Tuquan County, Xing'an League, Henan Engineering Company of China Electric Power Construction was terminated. The reason for termination is that "the owner of this project requires the commencement date to be advanced, the construction period is urgent, and the content of the bid section needs to be adjusted and re-tendered.". This tender is terminated.

2025-09-11 10:58:56

On the evening of September 10, Jinfeng Science and Technology announced that the company intends to sign the Agreement on Investment and Development of Wind Power Hydrogen Ammonia Alcohol Integration Project with Bayannaoer Municipal People's Government. Goldwind Science and Technology said that it plans to invest in the construction of wind power hydrogen ammonia alcohol project within the jurisdiction of Bayannaoer City, with a total investment of about 18.92 billion yuan. The overall plan of the project is to build 3GW wind power, more than 80% of which is used to electrolyze water to produce green hydrogen, and to produce 600000 tons of green methanol per year and 400000 tons of green ammonia per year by coupling biomass gasification with green hydrogen.

2025-09-11 10:10:35

On September 10, Beijing Energy Group Co., Ltd. held a cadre meeting to announce the decision of the Beijing Municipal Committee and the Municipal Government.

2025-09-11 09:29:04

On September 10, China Nengjian issued a tender announcement for the centralized procurement project of photovoltaic modules in 2025. The tender announcement shows that the total scale of the tender is estimated to be 17 GW, which is divided into 8 packages, covering 182 mm TOPCon components, 210 mm TOPCon components, HJT components and BC components. For this tender, in addition to good reputation and relevant qualifications, the bidder's performance requirements are as follows:

2025-09-10 17:55:52

On September 8, Weining Branch of Bijie Ecological Environment Bureau of Guizhou Province issued the first announcement of public participation in environmental impact assessment of "Weining County 5GW XBC High-efficiency Photovoltaic Cell Production and Construction Project".

2025-09-10 17:34:25

On September 9, the temporary land for CGN Fengning Manchu Autonomous County 200MW Photovoltaic Composite Demonstration Project was approved. The construction unit of this project is CGN New Energy Fengning Manchu Autonomous County Co., Ltd. It is reported that the temporary land for the project is located in Wudaoying Township (Wudaoying Village, Jiudaogou Village), Tucheng Town (Sanjianfang Village, Sijianfang Village) and Dage Town (Saerying Village) of Fengning County, covering a total area of 7.8342 hectares.

2025-09-10 09:38:41

Li Lecheng, minister of the Ministry of Industry and Information Technology, said of irrational competition in photovoltaic and other industries: "The cultivation of enterprises and industries can be described as untold hardships, and irrational competition destroys an enterprise and an industry, which may happen overnight. We must not tolerate this kind of thing." He said that the next step would be to adhere to the rule of law, strengthen industry self-discipline, implement regulatory responsibilities, and enhance service capabilities, so as to "address both the symptoms and the root causes, systematically govern, focus on improving the system and mechanism, optimize the industrial ecology, and constantly improve the modernization level of industry governance."

2025-09-09 16:20:34

On September 5, Yunnan Green Energy New Energy Development Co., Ltd. The announcement shows that due to the need of project development, the bidding activities of this project are suspended.

2025-09-09 09:41:09

Digital New Energy DataBM. Com learned that on the evening of September 7, Robertko announced that the company planned to issue shares abroad (H shares) and list them on the Stock Exchange of Hong Kong Limited.

2025-09-08 18:01:43

On September 4, Yunnan Green Energy New Energy Development Co., Ltd. issued a tender announcement for the first batch of centralized procurement of photovoltaic modules. The project construction unit is Yunnan Green Energy New Energy Development Co., Ltd., a subsidiary of Yuntou Group. The tender announcement shows that the total capacity of the centralized procurement agreement is estimated to be 400MWp, the components require monocrystalline silicon N-type double-sided double-glass 615Wp ~ 625Wp, and the contract price is estimated to be 300 million yuan.

2025-09-08 12:34:13

Digital New Energy DataBM. Com has learned that the photovoltaic module production line of Da'an Tianneng New Energy Equipment Co., Ltd. is to be transferred at a base price of 790,775 yuan (including tax) from August 4 to September 26, 2025.

2025-09-05 18:15:43

On September 5, Daqin Electric Power (Kunming) Group Co., Ltd., a subsidiary company of "Shaya County Qin Power Investment New Energy Co., Ltd. 490000 kW Photovoltaic Sand Control" EPC Project (2025), announced the successful candidate.

2025-09-05 14:54:14

Recently, the Digital New Energy DataBM. Com has learned that two more central energy and power enterprises have transferred their shares in new energy enterprises, involving the State Energy Group and the Three Gorges Group. Details are as follows:

2025-09-05 14:53:32

According to the news, Wang Bin was removed from the post of Deputy Secretary of the Party Committee, Standing Committee of the Party Committee and Director of China Electric Power Construction Group Co., Ltd. and no longer served as General Manager of China Electric Power Construction Group Co., Ltd. and retired.

2025-09-05 10:35:07

On August 29, the tender announcement for the general contracting project of the State Power Investment Daqing Dumeng Duishan Phase II 200 MW Grass Complementary Project was issued, and the tenderer was Heilongjiang Electric Power Co., Ltd. of the State Power Investment Group. The bidding content shows that the project is located in Duerbote Mongolian Autonomous County, Daqing City, Heilongjiang Province. The construction scale of the project is 200MW. The 220kV booster station and outgoing line are shared with the first phase of the 100MW project. In this phase, the main transformer, SVG, expansion of incoming line spacing and other related facilities are added. The booster station is connected to the outline substation with one circuit of 220 kV outgoing line (completed).

2025-09-04 10:28:32

The "low price competition" in the component market continues.

2025-09-03 18:00:00

On August 29, the tender announcement for PC contracting project of 150000 kilowatt beach photovoltaic power generation project (photovoltaic field and collector line) in Tongzhou Bay of Zhejiang Oilfield was issued, and the tenderer was CNPC Jiangsu Nantong New Energy Co., Ltd. The bidding content shows that the project is located in the jellyfish breeding area of Tongzhou Bay Demonstration Zone, Nantong City, Jiangsu Province (breeding Huajia, jellyfish, fish, crab, etc.), and the sea area of the project is about 2,271 mu. The new DC side capacity of the project is 179.26 MWp, the AC side capacity is 149.76 MW, and the capacity ratio is about 1.2. The project uses 248,976 720Wp monocrystalline double-sided modules.

2025-09-03 17:36:20

On August 25, China Anneng Electronic Procurement Platform issued a change announcement on the procurement project of photovoltaic modules for Lingwu 2 million kilowatt composite photovoltaic base project of China Anneng First Bureau Guoneng Lingshao DC, saying that the original announcement was invalid.

2025-09-02 15:36:56

On August 29, the Hebei Development and Reform Commission announced "the second batch of projects to be arranged in the annual development and construction plan of wind power and photovoltaic power generation in Hebei Province in 2025". This time, 81 projects will be announced, with a construction scale of about 7.49 GW, including 42 photovoltaic projects with a scale of about 3.13 GW. The main body of the project involves 12 central state-owned enterprises and 9 private enterprises, among which Xiexin Group and TBEA are two leading photovoltaic enterprises. Among the central state-owned enterprises, Huadian Group has the largest number of projects, 13 with a scale of 418000 kilowatts, Datang Group 4 with a scale of 710000 kilowatts, State Energy Group and South-to-North Water Transfer Group 3 with a scale of 2101300 kilowatts and 112000 kilowatts respectively.

2025-09-01 17:44:11

The Statistics of Domestic Concrete Prices in August shows the situation of concrete prices in various regions of China. From the overall data, prices in most regions have changed to varying degrees. On a month-on-month basis, prices in some regions remained stable, with small changes, while the month-on-month decline in Shaanxi was more obvious. On a year-on-year basis, each region also showed different changes, among which Shaanxi's year-on-year decline was relatively prominent, while Guizhou's year-on-year decline was unchanged. Nationwide, the month-on-month ratio decreased by 2.20% and the year-on-year ratio decreased by 18.38%.

2025-09-01 14:36:20

Recently, the Party Group of the Three Gorges Group held a meeting to inform the Organizational Department of the Central Committee of the Communist Party of China of the decision on the adjustment of the members of the leading group of the Three Gorges Group.

2025-08-29 10:07:03

On August 26, according to foreign media reports, the Federal Trade Court of the United States ruled that Auxin Solar and Concept Clean Energy were the plaintiffs. It ruled that the two-year (2022.6.6-2024.6.6) "Southeast Asia Solar Cell and Module Import Tariff Suspension Order" (hereinafter referred to as the "Tariff Suspension Order") implemented by the Biden Administration from 2022 was illegal.

2025-08-28 18:11:35

According to the list, there are 33 photovoltaic enterprises on the list, covering silicon materials, silicon wafers, components, batteries and other links.

2025-08-28 13:52:08

The Digital New Energy DataBM. Com was informed that on August 27, the EPC project of the 30 MW industrial and commercial photovoltaic project of China Yingjian New Energy Technology (Anhui) Co., Ltd. was changed.

2025-08-28 10:52:42

On August 23-25, Trina Solar, TCL Zhonghuan, Hengdian Dongci, Maiwei and other photovoltaic companies successively disclosed their recent investor relations activity records, sharing their views on the current domestic and overseas market trends and technological development judgments. Details are as follows:

2025-08-26 17:12:20

On August 21, Beijing Jingneng E-commerce Platform issued a tender announcement for EPC general contracting of agricultural photovoltaic power generation project in Zhangshanying Town, Yanqing District, Beijing.

2025-08-25 17:39:46

China's new energy storage is moving from large-scale to high-quality development, and will focus on technological innovation, efficiency improvement and sustainable development in the future.

2025-08-25 09:52:26

The high-quality development of new energy storage is the key support for the construction of new power system, which helps to improve energy efficiency and stability.

2025-08-25 09:52:09

By the end of July, the total installed capacity of power generation in China was 3.67 billion kilowatts, up 18.2% year on year. Among them, the installed capacity of solar power was 1 billion 110 million kilowatts, an increase of 50.8% over the same period last year.

2025-08-25 09:28:03

Digital New Energy DataBM. Com learned that Panda Photovoltaic Technology Co., Ltd. was filed for bankruptcy, the court was the People's Court of Binhu District, Wuxi City, Jiangsu Province, the applicant was Chen Tao, and the public time was August 21.

2025-08-24 12:18:13

This week, the overall performance of the PV module market continued to be weak.

2025-08-22 22:16:34

On August 22, the official of China Photovoltaic Industry Association issued an initiative on "further strengthening industry self-discipline and jointly maintaining the order of photovoltaic market with fair competition and survival of the fittest". Enterprises in the photovoltaic industry are required to strictly abide by relevant laws and regulations, and resolutely resist vicious competition at prices below cost; power plant enterprises optimize bidding rules, reduce price weight, and improve technical evaluation weight.

2025-08-22 18:28:23

On the evening of August 21, Yiwei Lithium Energy released its semi-annual report for 2025.

2025-08-21 10:58:10

After deliberation at the 16th meeting of the Eighth Presidium of the Chinese Academy of Engineering and approval by the Party Group of the Chinese Academy of Engineering, 660 valid candidates for the election of academicians of the Chinese Academy of Engineering in 2025 were confirmed.

2025-08-21 09:53:40

The market price of photovoltaic modules tends to be stable, with partial price reduction.

2025-08-20 18:11:35

On August 20, Guangdong Dongguan Public Resources Trading Platform issued a number of public bidding announcements for the rental of roof use rights, with a total transaction area of 11,544.08 square meters, limited to the construction of photovoltaic projects.

2025-08-20 18:10:45

On August 19, Yunnan Development and Reform Commission and Yunnan Energy Bureau issued a notice on the issuance of the second batch of new energy project development and construction plans in Yunnan Province in 2025.

2025-08-20 09:43:48

Prices in Ningxia are stable but export sales are low, Gansu is facing callback pressure after price increases, sales in Qinghai are not up to expectations after pushing up, Shaanxi has great resistance to price recovery, Xinjiang is stable due to engineering demand, and the overall market is mainly stable price wait-and-see in the short term.