On January 22, the Heilongjiang Provincial Office of Industry and Information Technology issued a public announcement on the replacement plan for the 8450 tons per day cement clinker production line project of Jidong Cement Heilongjiang Co., Ltd. As well as the announcement of the supplementary capacity replacement plan for the No.1 and No.2 cement clinker production line projects of Heilongjiang Pennsylvania Cement Co., Ltd. with a daily output of 5750 tons. The publicity period is within 10 working days from now on. Cement clinker production line project with a daily output of 8,450 tons
of Jidong Cement Heilongjiang Co., Ltd.: The original design daily output is 7,200 tons, and the supplementary daily output is 1,250 tons.
Transferred capacity: 2500t/d production line of Liaoyang Jidong Cement Co., Ltd., with replacement ratio of 2:1. No.1 clinker production line project with a daily output of 5,750t of
Pennsylvania Cement Co., Ltd.: It has a production capacity of 5,000t/d, with a replacement capacity of 750t/d.
Transfer-out capacity: 1500t/d capacity of Dalian North Cement Co., Ltd., replacement ratio 2:1. No.2 cement clinker production line project with a daily output of 5,750 tons of
Pennsylvania Cement Co., Ltd.: It has a production capacity of 4,500t/d, with a replacement capacity of 1,250t/d.
Transfer-out capacity: 2500t/d capacity of Dalian North Cement Co., Ltd., replacement ratio 2:1.