The Digital New Energy DataBM. Com was informed that on August 27, The EPC project of the 30 MW industrial and commercial photovoltaic project of China Yingjian New Energy Technology (Anhui) Co., Ltd. has been changed .
The announcement shows that the supervision section of the project has been terminated due to major adjustments .
At the same time, The bid opening time of the first bid section "EPC Project of 30 MW Industrial and Commercial Photovoltaic Project of Zhongyingjian New Energy Technology (Anhui) Co., Ltd." Originally scheduled at 9:00 on August 29 will be postponed to 9:00 on September 1.
It is understood that the project fund is 93.8781 million yuan , which is planned to be built on the industrial and commercial roofs of Alashan Left Banner in Inner Mongolia, Ordos City in Inner Mongolia and Yinchuan City in Ningxia. The total installed capacity of the distributed photovoltaic power station is 36 MWp/30 MW, and 12 MWp/10 MW in each of the three regions.
The project is divided into two bid sections , one of which is the EPC project of 30 MW industrial and commercial photovoltaic project of China Yingjian New Energy Technology (Anhui) Co., Ltd; The second bid section is the EPC project supervision of the 30 MW industrial and commercial photovoltaic project of China Yingjian New Energy Technology (Anhui) Co., Ltd.
In addition, the planned duration of the project is 180 calendar days .