Digital New Energy DataBM. Com learned that on December 5, Xinjiang Tuha Oilfield Turpan Shanshan East 1 million kilowatt announcement" showed that the project is located in the railway station town of Shanshan County, Turpan City, Xinjiang. The total installed capacity is 1 million kilowatts , and the tenderer is Tuha Oilfield Branch of PetroChina Company Limited.

The project is divided into five bid sections , one of which is responsible for EPC of 220 KV gathering station and energy storage power station ; The second bid section is responsible for the EPC of photovoltaic southwest area, with a total installed capacity of 336 MW, consisting of 70 4.8 MW photovoltaic sub-arrays; The third bid section is responsible for the EPC of photovoltaic northwest area, with a total installed capacity of 192MW, consisting of 40 4.8MW photovoltaic sub-arrays; The fourth bid section is responsible for EPC of photovoltaic southeast area, with a total installed capacity of 227 MW, consisting of 47 4.8MW and 1 1.5MW photovoltaic sub-arrays; The fifth bid section is responsible for the EPC of photovoltaic northeast area, with a total installed capacity of 245MW, consisting of 51 4.
Performance requirements for bidders from January 1, 2022 to the deadline for bidding. The bidder shall have the performance of EPC general contracting or design or construction general contracting for at least one photovoltaic power generation project of 100MW or above .
In addition, the project plans to complete the main construction from the date of signing the contract to August 31, 2026, and has the conditions for joint commissioning. Consortium bidding is not accepted for
this project .
The bid deadline and bid opening time are 8:00 on December 29, 2025.