Digital New Energy DataBM. Com was informed that on November 25, the results of EPC general contracting for the photovoltaic area of Luntai 200000 kW photovoltaic power generation project in Tarim Oilfield, Xinjiang, were announced.
According to the announcement, the winning bidder , China Construction Fourth Bureau Installation Engineering Co., Ltd. , won the bid at a price of 63.7355 million yuan .

The tender announcement shows that the project is located in Jigedaiquele Village, Luntai County, Bazhou, Xinjiang , with a total installed capacity of 200000 kilowatts. A 220 KV booster station and a 20 MW/40 MWh lithium iron phosphate battery energy storage station will be built, and a 5.7 km 220 KV overhead line will be connected to Lunnan 220 KV substation.
The project was originally planned to start on November 20, 2025, the main project was completed on June 30, 2026 and has the conditions for grid connection, the grid connection on July 30, 2026, and the full capacity grid connection on October 30, 2026. (Related Reading: Xinjiang 200 MW PV Project EPC General Contracting Bidding! )
浙公网安备33010802003254号