On July 25, Huaneng Shaanxi Company issued a tender announcement for purchasing 19 MW photovoltaic modules for the photovoltaic project in Kekedala City, the fourth division of Xinjiang, and the tenderer was Huaneng Kekedala New Energy Co., Ltd.
The project is located in the west of Kekedala City, Xinjiang Uygur Autonomous Region, with an AC side capacity of 300MW. A new 220kV booster station is connected to the 66th regiment substation with a 220kV double-circuit overhead line. The energy storage system of 45MW/90MWh is configured, and the full capacity is planned to be connected to the grid in October 2025. The scope of this
tender is the supply and transportation of double-sided double-glass heterojunction (HJT) modules of 19 MW 700Wp and above.