The Digital New Energy DataBM. Com was informed that on November 11, yuanmou Branch of Chuxiong Ecological Environment Bureau of Yunnan Province issued a public announcement on the acceptance of environmental impact assessment of Mengling Gou Photovoltaic Power Station Project of Datang (yuanmou) New Energy Co., Ltd. According to

the EIA documents, Menglinggou Photovoltaic Power Station Project of Datang (yuanmou) New Energy Co., Ltd. is a new project , located on the hillside near Sanzhi Village, Wumao Township, yuanmou County, Chuxiong Prefecture, Yunnan Province, with a rated capacity of 60 MW. The installed capacity is 72.788 MWp, and the total investment 65734 is 0.69 million yuan .

The project plans to install 650 Wp monocrystalline silicon photovoltaic modules with 112000 blocks, consisting of 4000 strings of 24 photovoltaic arrays and 200 inverters. There are 24 box-type transformers, and the collected power is connected to the 220kV booster station with 2 collecting lines. The total land area of
the project is 92.07 hm2 , including 14.65 hm2 of permanent land. The temporary land occupation is 77.42 hm2 . The total construction period is 6 months .
Prior to this, Datang (yuanmou) New Energy Co., Ltd. has completed the project filing in February 2025.