The Digital New Energy DataBM. Com was informed that on July 16, The procurement of photovoltaic modules and fixed brackets for the 452 MW fishing-photovoltaic complementary photovoltaic power generation project of Jiangsu Yinbao Xinnongyuan Science and Technology Co., Ltd. was terminated.
As for the reasons for the termination, the tenderer Shandong Electric Power Engineering Consulting Institute Co., Ltd. explained in the announcement that the main reason was the change in the procurement demand of the project, and the procurement of photovoltaic modules and fixed brackets was terminated.
According to the tender announcement issued on July 14, the project is located in Sheyang Salt Farm, Sheyang County, Yancheng City, Jiangsu Province , and started construction in April 2025. Completion is scheduled for October 2026. Its procurement scope includes 640Wp N-type double-sided photovoltaic modules and zinc-aluminum-magnesium steel structural brackets.