Provincial Highway S319 Changli to Wanglanzhuang Highway Wangzhuangzi to Sheliu Section Construction Project Design and Construction General Contracting Successful Candidate Announcement
Construction Location: Changli County, Qinhuangdao City
Construction Scale: The total length of the route is 9.994 km. 5 medium bridges of 199m, 13 culverts and 3 grade road intersections are newly built along the whole line. The whole line is constructed according to the first-class highway standard, with a design speed of 80 km/H and a roadbed width of 25.5 meters. The design vehicle load grade of bridges and culverts is highway-I.
Construction period: 25 months, including 1 month of survey and design period, 24 months of construction period, planned commencement date: October 1, 2025, and 24 months of defect liability period.
Bidding scope: complete the detailed survey, location survey and construction drawing design of the construction project of Wangzhuangzi-Sheliu Section of Provincial Highway S319 Changli-Wanglanzhuang Highway as required, as well as all related work in the construction preparation stage, construction stage and defect liability period stage.
Bid winning information:
First place: CCCC First Harbor Engineering Co., Ltd.
Consortium
of CCCC Highway Planning and Design Institute Co., Ltd. Bid price (RMB): 225509615
Second place: CCCC Road & Bridge Construction Co., Ltd. 0 HTML0 2269410830 0 Zhonggui Dihuan Survey and Design Co., Ltd. 0 HTML0 UNK1 1 Consortium of Hebei Shuiyi Mufeng Engineering Technology Co., Ltd. 0 HTML0 UNK1 2 Bidding Price (RMB): 2269410830 HTML0 UNK1 3 Third Place: China Railway Siju Group Co., Ltd. 0 HTML0 UNK1 4 Chuanghuida Design Joint Stock Limited Company Consortium 0 HTML0 2258294880 5 Bid Price (RMB): 2258294880 HTML0 UNK1 6