The Digital New Energy DataBM. Com was informed that on July 15, China Nuclear Huineng announced the result of EPC general contracting of 90 MW fishing-photovoltaic complementary photovoltaic project in Haiwei Town, Changjiang County, Hainan.
The announcement shows that the consortium composed of China Nuclear Industry 23 Construction Co., Ltd. and China Electric Power Construction Group East China Survey and Design Research Institute Co., Ltd. has successfully won the bid for the project at a price 24400.05 10000 yuan .
According to the previous tender announcement issued on May 16, the project is located in Haiwei Town, Changjiang County, Hainan Province, with a planned installed capacity of 90 MW . The project will use the existing aquaculture ponds to build a fishing-light complementary complex project.
In terms of schedule, the project is scheduled to start on August 1, 2025 and achieve full capacity grid connection on January 28, 2026. The total construction period is 180 days (to full capacity grid connection). It should be noted that the project shall complete the completion acceptance and file handover within 4 months after the completion of full capacity grid connection.