Digital New Energy DataBM. Com learned that on July 14, Hunan Chendian New Energy Development Co., Ltd. issued the announcement of the first batch of successful candidates for photovoltaic module procurement (the third time) in 2025.
The announcement shows that three enterprises were selected , namely Chenzhou Chendian Technology Co., Ltd., Wuhan Jiuheng Volkswagen Technology Co., Ltd. and Hunan Dalong New Energy Development Co., Ltd . The details are as follows:
It is worth noting that the previous two tenders for the project were rejected because there were less than three qualified bidders in the bid evaluation. (For details, please click: The PV module procurement project of a state-owned enterprise in Hunan was rejected for the second time! )
According to the previous tender announcement, the total investment of the project is 16.5 million yuan , and the estimated installed capacity is 90 MW . The tender plan shows that the tender aims to ensure that Hunan Chendian New Energy Development Co., Ltd. has sufficient supply of photovoltaic components for new construction, reconstruction and expansion of photovoltaic power stations and supporting facilities .
In terms of construction period arrangement, the project requires the successful bidder to start supplying goods 5 days after receiving the supply order from Party A, and the supply period is 12 months from the date of signing the contract; If the consumption does not reach the total amount of supply, it can be extended appropriately according to actual needs, and in principle , it shall not exceed 18 months .