According to Huangshi Daily, the first phase of Yangxinwa Stone Mine's green environmental protection material project with an annual output of 10 million tons of machine-made sand production line has been completed for trial production, which can reach the standard in August and September.
According to reports, Yangxin Washi Mine Investment Green Environmental Protection Material Project is a provincial key project invested and constructed by Washi Cement Group Co., Ltd. (Hereinafter referred to as "Washi Group") and Yangxin County Mining Investment Company. The total investment of the
project is 1.6 billion yuan, which is divided into two phases. Among them, a 10 million tons/year machine-made sand production line will be built in the first phase, and a 10 million tons/year machine-made sand production line will be built in the second phase. After the completion of the project, the annual output value will be 1.8 billion yuan, the tax revenue will be 400 million yuan, and 600 jobs will be provided, which will promote the economic development of the local village groups.
At present, the second phase of the green environmental protection material project is under construction with an annual output of 10 million tons of machine-made sand, which is expected to be put into operation by the end of 2025.